Valley Traffic
Congestion Eases As Expressway Project Continues
TxDOT Expands Intersection Where
Two Highways Meet In South Texas
By Mark Rea
Increasing volumes of truck traffic heading north from Mexico
have combined in recent years with scores of Winter Texans
heading south to cause roadway congestion throughout the Harlingen
area of South Texas.
The Texas Department of Transportation began to address the
problem in April 2001 when it kicked off construction of upgrades,
improvements and expansion of the location in Cameron County
where U.S. Highway 83 empties its eastbound traffic into north
and southbound U.S. 77.
TxDOT took the traffic flow problem so seriously that it has
let more than $61.3 million over a 3½-year period on
the project to relieve the area's congestion.
Houston-based Williams Brothers Construction Co. Inc. is
the general contractor for the 4.98-mile project, which includes
five phases: installation of a new storm sewer system; construction
of new main lanes in the center section including bridges;
reconstruction of north and southbound main lanes including
bridges and retaining walls; and construction of median barriers
and illumination.
"Phases I and II are pretty much complete and now we
have started Phase III, which is reconstructing the southbound
portion of U.S. 77/83," said TxDOT project engineer Rene
Garza.
The southbound portion of the project is expected to be completed
in February 2004 with the entire expressway finished in March
2005.
Since the enactment of the North American Free Trade Agreement
between Canada, the United States and Mexico in 1994, truck
traffic making its way north on U.S. 77 from the border towns
of Matamoros and Brownsville has steadily increased.
As NAFTA traffic moved north toward Interstate 37 and San
Antonio, other truckers chose to head west along the Rio Grande
to Laredo before making their way to the Alamo City and points
north.
At the same time, Midwesterners and New England residents
wishing to escape their brutal winters at home as well as
avoid the population explosion in Florida, began to seek their
winter solace in the most southern regions of Texas along
the Gulf of Mexico.
The result clogged roadways designed in the 1950s and 1960s
for approximately one-third the traffic volume it was experiencing.
"There is so much traffic right now that the existing
roadway simply couldn't handle the volume we experience on
a day-to-day basis," Garza said. "It was obvious
that we had to expand this expressway from two lanes to three
in each direction just to handle the traffic we have now.
"In Harlingen, where U.S. 77 and U.S. 83 meet, we receive
vehicles traveling from both north and south as well as east
and west. In the first half-mile where the two highways merge,
there are four lanes but then it reduces down to three. It
has been a bottleneck and headache for drivers in this area
for some time."
And it's not just NAFTA traffic or Winter Texans in their
SUVs and motor homes causing the congestion.
"Many of the vehicles on the expressway are used each
day just to get to and from work," Garza said. "For
instance, I live on the McAllen side of the Valley and have
to drive about 40 or 45 miles east to Harlingen or San Benito
every day. There are tens of thousands of drivers who make
the very same commute. Many others drive about the same distance
north from Brownsville daily.
And then, of course, we all turn around at the end of the
work day and head back to our homes. It makes for a huge volume
of traffic for a roadway that really wasn't designed for it."
Getting Started
At the beginning of the project, workers had to deal with
what to do about the volume of traffic around the interchange
area where the two highways meet.
On one side of the expressway, the sprawling Valle Vista
shopping mall features many of the most popular retail stores
and restaurants in the area. On the opposite side are the
most populated areas of Harlingen.
"The problem that generates with construction is that
we have to keep that traffic flowing yet still construct around
it," Garza said. "The logistics of lane closures,
switching traffic and keeping it moving through the area was
a large obstacle to overcome."
But as the project took shape, the eight overpasses that
were the major components of the project helped to alleviate
much of the traffic headaches. The new overpasses allow traffic
to navigate freely above Lincoln, Louisiana and New Hampshire
avenues, M and F streets, Farm-to-Market Road 1479, Ed Carey
Drive and FM 509. Additionally, motorists making their way
on the streets and roadways beneath the overpasses will enjoy
a marked reduction in traffic flow.
Decorative precast retaining walls are currently being installed
along the ramps leading to and from the expressway while frontage
roads will feature three lanes for increased access and egress.
Several hundred tons of fill dirt was needed for the new
ramps and expanded expressway. "The project is pretty
much all fill because this highway was built more than 20
years ago," Garza explained. "Some of the vertical
curves over the bridges were designed for only 50 or 55 mph
and now we have upgraded those so vehicles can move through
there at up to 70 mph. Therefore, the length of the curves
going over the bridges has to be longer so there is a lot
more fill that needs to be added."
Seven of the eight overpass intersections will be paved with
an asphalt permeable friction course.
Williams Brothers will supply its own hot mix and also self-perform
bridge work for the project.
Demolition Phase
One of the most unique parts of the project took place as
crews demolished existing bridges to make room for the new
expressway lanes. According to Garza, removal of the bridges
entailed more than simple demolition.
"One of the bridges spans the Colorado River and we
have to consider environmental problems," he added. "You
can't allow pieces of concrete to fall into the water, so
crews were forced to saw cut the bridge decks into large pieces
which were then removed from the site."
As crews chopped the deck, abutments and piers into manageable-sized
pieces, other workers using front-end loaders, bulldozers
and dump trucks loaded the concrete to be hauled away. The
concrete, rebar and any other usable material was to be recycled,
either back into the project or another similar project in
the area.
"Also when we demolish the bridges, we have to close
the intersections and divert traffic," Garza said. "We
also have to close the frontage roads down to just one lane
and that causes a lot of headaches for the motorists. We know
that and we're sympathetic to them. But we also know that
once the demolition phase is over, we can get that traffic
back to a more normal flow. And once this project is complete,
it will make a huge difference for the motorists in this area."
Messaging Technology
The expanded roadways will feature the latest in messaging
technology from TxDOT. At least four huge message boards are
being installed throughout the area, including two already
in use:
southbound on U.S. 77 and eastbound on U.S. 83. At least two
more are scheduled to be installed by San Benito-based V.C.
Huff Inc.
Tied into the statewide TxDOT information network, the boards
can quickly convey road conditions, lane closures and up-to-the-minute
accident locations. The boards can also carry information
regarding Amber Alerts to help locate missing children.
Garza said there was no major utility relocation for the
project. "There was a little bit of that such as moving
some lines over to install the new storm sewers in phase one,"
he said. "But that's pretty typical for a project like
this one. There really was nothing major in terms of utility
relocation."
A workforce of more than 200 was onsite in late March at
the project. Work schedules were typically 5-10s with some
subcontractors working modified schedules - such as late-night
work - to keep the impact to traffic at a minimum.
And while Williams Brothers continues work on the U.S. 77/83
expansion, the company recently kicked off construction of
another large-scale TxDOT project in the area: the $82.5 million
expansion of U.S. 83 through Weslaco between Harlingen and
McAllen.
|
PROJECT TEAM
|
|
GENERAL CONTRACTOR: |
Williams Brothers Construction
Co. Inc., Houston |
|
LOCATION: |
Harlingen |
|
OWNER: |
Texas Department of Transportation |
|
STRIPING: |
Lindas Construction Inc.,
Kingsville |
|
CURBS, GUTTERS: |
Leal Construction
Inc., Olmito |
|
GUARDRAILS: |
Central Texas Guardrail
Inc., Wimberley |
|
MESSAGE BOARDS: |
V.C. Huff Inc., San Benito |
|