Houston Welcomes Third New Professional Sports Venue
Facility Will Be Home To NBA, WNBA, AHL Franchises
By Mark Rea
Houston's construction industry has continually bucked the
economic downturn of the past couple of years with high-rise
office towers, new highways and multi-million-dollar sports
venues such as Minute Maid Park and Reliant Stadium.
As those facilities get set to host the 2004 Major League
Baseball All-Star Game and Super Bowl XXXVIII, respectively,
they will be joined by the third jewel in Houston's professional
sports arena crown: the Toyota Center.
The Houston office of Hunt Construction Group managed construction
of the $220 million arena, which will replace Compaq Center
as the new home for the Houston Rockets of the National Basketball
Association, the Houston Comets of the WNBA and the Houston
Aeros of the American Hockey League.
Boasting 755,000 sq. ft., the facility seats 18,500 for basketball
games, 17,800 for hockey contests and up to 19,300 for other
events such as concerts. It is located in the heart of downtown
Houston near the newly expanded George R. Brown Convention
Center and the soon-to-be completed Hilton Americas hotel.
With nearly 100 different companies contracted to perform
work on the arena - and the owner, Harris County and other
organizations supplying input - coordination and collaboration
were key components to the project. Many of the subcontractors
on the job were Houston-area companies and more than 30 percent
of those were minority or women-owned.
"It was extremely important to us that this project had
a local appeal and local flavor during construction,"
said Hunt Construction project executive Mike Fratianni. "It
was a goal of ours to involve as many local contractors in
the Houston community and make sure they had the opportunity
to work on what should be the last major sports venue built
in this city for at least the next 25 or 30 years. That started
from the top with Hunt's role as construction manager."
Two more Houston-based companies quickly signed on to the
project. Tellepsen LP, one of the area's most established
construction firms, won the contract to build the arena's
1-million-sq.-ft., 2,500-vehicle parking garage. The Trevino
Group, one of the community's fastest-growing, Hispanic-owned
construction companies, also provided project superintendents
as well as MWBE coordinator Gilbert De La Cruz.
Official groundbreaking took place July 21, 2001, on four
downtown blocks that had previously been the site of various
small businesses, a fire station and a Houston Light &
Power distribution control office.
All structures were demolished and foundations excavated.
Because several of the businesses had used different types
of chemicals over the years, the Texas Commission on Environmental
Quality handled oversight of the removal of all materials,
including the remediation process that was employed before
actual construction could begin. Under TCEQ controls, all
excavated material removed from the site during the entire
24-month construction period was classified as Class 2 environmental.
Getting Started
Actual construction began in September 2001 with excavation
of more than 300,000 cu. yds. of dirt, which was removed and
recycled for industrial-only sites. Crews dug approximately
32 ft. below grade for the arena footprint, something unusual
for the Houston area.
"From a construction standpoint, perhaps the most remarkable
aspect is the depth of the arena into the ground," Fratianni
said. "For this facility to be more than 32 ft. below
street level is remarkable. Most of these arenas are not nearly
that deep, and couple that with the fact that this is Houston
with a rather shallow water table and the depth is quite unique."
Because Houston is a designated hurricane zone, the arena
project had to be designed with an elaborate dewatering system
complete with a series of redundant floodgates and an extensive
network of drainage and pumps. In conjunction with Houston-based
project engineer Walter P. Moore & Associates Inc., the
dewatering system was designed and installed by two other
area companies: Ulrich Engineers Inc. and Griffin Dewatering
Southwest LLC.
"This is one of the most extensive dewatering systems
I have ever seen," said project architect Scott Watkins
of Houston-based Morris Architects. "This facility will
stay dry from existing groundwater and any street-level flooding
that may occur. The system added a bit to the overall project
cost, but I think it will be worth every penny."
The arena's exterior sits atop approximately 450 drilled piers,
which featured average diameters of 30 in. W&W Foundation
Inc. of Houston handled drilling of the piers to depths of
between 60 ft. and 80 ft. The piers are capped with a 4-by
4-ft. concrete beam at grade level to support the building.
Once drilling was completed, crews made sure the dewatering
system was protected with sand and gravel layers beneath a
mud slab.
"We had to make everything underneath the floor able
to drain water into sump pumps, so there is a lot of perforated
pipe put in along with sand and gravel layers," said
Jim McLain, Hunt Construction project manager. "Atop
those layers is the mud slab, and then we poured a finished
8-in. slab of concrete."
Baker Concrete Construction Co. of Houston handled the tunnel
and ramp areas of the project while the Carrollton and Houston
offices of Capform Inc. took care of the superstructure and
slabs. Another Houston firm - Sterling Steel - furnished the
reinforcing steel for the project.
Separate Superstructures
Two separate superstructures comprise the Toyota Center.
One is reinforced concrete, the other steel. Pours for the
concrete portion of the facility began in February 2002 and
were completed seven months later.
Also during that period, concrete was poured for the raker
beams that support the upper seat decks and for smaller rakers
that support the two levels of private suites.
Raker beams feature a unique stair-step effect that eventually
bears the weight of the precast concrete seating bowl.
Corpus Christi-based Heldenfels Enterprises Inc. supplied
and installed the structural precast concrete.
Structural steel erection began in October under the supervision
of Havens/FabArc of Kansas City, Mo. The 175,000-sq.-ft. arena
roof is supported by four steel supercolumns, situated on
the main concourse of the arena about 35 ft. above the event
level.
"The supercolumns were a driving design feature of the
building," Fratianni said. "The owners very much
wanted the supercolumns structure to be a major feature in
the seating bowl."
Each supercolumn rises 70 ft. to support two huge steel supertrusses,
which crisscross the arena diagonally just below the roof.
"Each supertruss is 35 ft. deep and supports numerous
smaller trusses, which run parallel to the event level,"
said Hunt Construction project engineer Paul Wojciechowski.
"The smaller trusses support the steel roof joists. The
roof of the arena is comprised of steel deck covered with
insulation, sealed with a single-ply membrane known as Sarnafil."
McLain, who participated in construction of the Louisiana
Superdome in the mid-1970s for Hunt Construction, said the
supertrusses and design of the roof system are unique. "It's
a much more lightweight structure for a roof system than you
would typically see on an arena like this," he added.
"In many ways, this structure resembles the Superdome
and, even before that, the Astrodome.
"And even though the roof structures for those facilities
are obviously much larger than this arena - I can still remember
the area of the Superdome roof covers nine acres - the similarities
are there. The major difference here is the weight. With Walter
P. Moore's design, those steel supercolumns and supertrusses
allow for a much more lightweight roof, which translates into
many things, including reduced construction costs."
Designers also placed the facility's cooling tower atop the
adjacent parking structure in order to keep the clean, unobstructed
lines of the arena's domelike roof.
"That was something else that was unusual," McLain
said. "The cooling tower for the arena is not directly
attached to the arena itself. But again, it was ingenuous
design because we could bring all of the piping up through
those large areas between the service and main concourse levels
and then tie them into the cooling tower on the parking garage
through the roof of the skybridge."
Despite the intricacy of the erection, the project utilized
only one tower crane. "But we employed an army of crawler
cranes," McLain said. "For instance, when the concrete
was being poured, more than a half-dozen cranes were being
used inside the circumference of the arena and several more
were outside the perimeter for erection of the architectural
precast."
The arena features six different levels: service, event, main
concourse, mezzanine, suite level and upper concourse. The
public will enter at the main concourse level through the
lobby on the arena's northwest corner.
Suites Above And Below
Since the event floor is located below the main concourse
level, the Toyota Center features the latest innovation in
luxury suites: 14 courtside bunker suites.
The suites are tucked below the seating bowl on the event
level and patrons can use their own staircases to move between
their seats at courtside and the suites, which are equipped
with state-of-the-art electronics.
The courtside suites are exclusively served by a bunker suite
lounge and feature their own restroom facilities.
In addition to those suites, there are 82 luxury suites divided
between two of the arena's upper levels. Additionally, three
large party suites were included to allow small businesses
or individuals to purchase premium seating.
The workforce hit a peak of 650 in March and remained at that
level for the next four months. Then at the beginning of July,
the sprint toward the Sept. 1 completion began.
"We divided the finish-out part of the project into 12
separate sectors," McLain said.
"That was because we need to get some sectors completed
before others at the owner's request. For example, the Rockets
wanted to begin installing furniture in some of their administrative
offices on Aug. 1, so we concentrated our efforts there."
The Rockets will kick off their inaugural season in the Toyota
Center beginning in October. Since moving to Houston from
San Diego in 1971, the team enjoyed 15 straight winning seasons
from 1985 to 1999 and back-to-back NBA championships in 1994
and 1995. But the franchise has struggled recently, posting
losing records in two of its last four seasons and falling
short of the Western Conference playoffs in 2003 despite an
improved 43-39 record.
With new head coach Jeff Van Gundy and such young NBA stars
as Steve Francis and Yao Ming, the Rockets hope their move
into a new arena will benefit them the way a similar move
helped the San Antonio Spurs, who walked off with the 2002-03
league championship trophy in their first season in the SBC
Center.
Not that the Comets or Aeros can't fill the new arena with
championship banners of their own. The Comets won four consecutive
WNBA titles from 1997-2000 and the Aeros will head into their
new home as defending Calder Cup champions of the AHL.
| PROJECT
TEAM |
| CONSTRUCTION
MANAGER : |
Hunt Construction Group,
Houston |
| LOCATION: |
Houston |
| OWNER: |
Harris County Houston
Sports Authority |
| ARCHITECTS
OF RECORD: |
Morris Architects, Houston
(arena); Prozign Architects (garage) |
| DESIGN
ARCHITECT : |
HOK Inc., Kansas City,
Mo. |
| ASSOCIATE
ARCHITECT: |
John S. Chase Architects
Inc., Houston |
| GENERAL
CONTRACTOR: |
Tellepsen LP, Houston
(garage) |
| ASSOCIATE
CONTRACTOR: |
The Trevino Group, Houston |
| STRUCTURAL/CIVIL
ENGINEER: |
Walter P. Moore &
Associates Inc., Houston |
| MECHANICAL
ENGINEER: |
Way Engineering Ltd.,
Houston |
| ELECTRICAL
ENGINEER: |
Melton/ERMCO LLC, Houston |
| PLUMBING
ENGINEER: |
Har-Con Enterprises,
Houston |
| STRUCTURAL
STEEL: |
Havens Steel Co., Kansas
City, Mo. |
| PRECAST
CONCRETE: |
Heldenfels Enterprises,
Corpus Christi |
| CONCRETE
CONTRACTORS: |
Capform Inc., Houston
and Carrollton (superstructure and slabs); Baker Concrete
Construction Inc., Houston (tunnel and ramp) |
| MASONRY: |
Easthaven Inc., Houston |
| TERRAZZO
FLOORING: |
National Terrazzo &
Tile Co., Houston |
| DEWATERING
SYSTEM: |
Ulrich Engineers Inc.,
Houston (design); Griffin Dewatering Corp., Houston (installation) |
|