NTTA,
TxDOT Partner For Construction Of Tollway Extension, Interchange
Three-Level, $31 Million Project Will Connect Toll Road With State Highway
By Mark Rea
The North Texas Tollway Authority is teaming with the Texas
Department of Transportation to complete a $31 million highway
project in a rapidly growing city just north of Dallas.
Construction of the Dallas North Tollway Extension and Interchange
at State Highway 121 began in early 2002 just south of Frisco,
an area where TxDOT was planning improvements to SH 121.
"As we got into development of the project, working with
TxDOT and its plans to expand SH 121, it quickly appeared
that both of us would be trying to do construction projects
in the same area at or close to the same time," said
Mark Bouma, NTTA director of engineering. "The idea was
developed to create a combined project, specifically at the
interchange, and we designed for TxDOT the portion of SH 121
that moves through the interchange."
Houston-based Kellogg Brown & Root is the construction
manager for the three-level interchange project and the Austin
office of Balfour Beatty Construction Inc. is the general
contractor.
The levels - which can be expanded to five in the future -
include a frontage road intersection, SH 121 main lanes in
the middle and tollway main lanes at the top. Had the project
continued as two separate projects, it would have necessitated
TxDOT constructing an additional bridge later between the
completed first and third levels.
"It's rare but not that unusual for us to do work with
other entities," said Bill Goodell, TxDOT Dallas district
construction engineer. "Either they do the work and we
pay for it or vice versa. Here in the Dallas area, for example,
we have done the same type of things with (the Dallas Area
Rapid Transit Authority) and NTTA on the tollway and the George
Bush Turnpike.
"In this case, the tollway wanted its portion of the
project completed before we were scheduled to begin. We already
had two projects under way on SH 121: one on the far east
side at U.S. Highway 75 and one on the far west end at Interstate
35.
"We were going to be redoing SH 121 through that area
sequentially, but it was going to be awhile before we actually
got to that interchange. The tollway authority proposed that
they do the work and we could simply reimburse them, and that's
how the collaboration came about."
Goodell said the collaboration has gone smoothly. "The
tollway authority is limited in the number of staff it has,
so it has a construction manager," he added. "It's
KBR in this case, and we have worked quite frequently with
them over the past few years, especially on the George Bush
Turnpike. We have also worked with Balfour Beatty as well,
so we were comfortable with that arrangement."
TxDOT also continues to perform periodic oversight inspections
on the project.
Response To Growth
The project is part of the NTTA's capital improvement program
as the tollway begins its initial extension into Frisco. It
is located just south of the burgeoning city's new sports
complex, which features newly completed minor-league baseball
and ice hockey venues.
Statistics show that 60,000 to 70,000 vehicles use that SH
121 corridor daily in addition to up to 30,000 more on the
Dallas North Tollway.
"We wanted to extend the tollway at least over SH 121
to give our patrons increased mobility and alleviate some
of the traffic congestion in that particular area," Bouma
said. "That particular part of Collin County is experiencing
a tremendous amount of growth."
The project will contain more than 110,000 sq. yds. of continuously
reinforced concrete pavement when completed. Noel Ibrahim,
chief engineer/construction for the NTTA, said there will
be 93,000 sq. yds. of 10-in. pavement on the DNT and 17,300
sq. yds. of 11-in. pavement on SH 121.
"In addition, we are building very short lanes on SH
121 and transitioning about 17,000 sq. yds. of 8-in. pavement,"
she said.
The project will also contain nearly 235,000 sq. ft. of bridge
work although no direct-connect ramps are part of the project.
"This will be a signalized intersection," Bouma
said. "There are already master plans to connect SH 121
via ramps to the east of the DNT, and the schematics for those
ramps have already been approved. But they are not part of
this particular project."
The tollway extension and intersection features drilled-shaft
construction. "We were very fortunate with this project
that the rock base in the area is relatively shallow,"
Ibrahim said. "The piers were drilled to about 15 ft.
below the surface."
Each conventional cast-in-place pier averaged in diameter
between 36 in. and 48 in.
Balfour Beatty supplied its own concrete for the project from
an onsite batch plant located near the new Dr Pepper/7 Up
Ballpark at the Frisco Sports Complex. Dallas-based TXI has
also provided concrete specialties for the project, and the
Lofland Co. of Fort Worth supplied the reinforcing steel.
Earthmoving occupied a large portion of the early stages of
the project as approximately 457,000 cu. yds. of materials
were excavated and then used for various embankments in the
extension and interchange. Some excavated material was also
removed from the site and stored for future DNT extensions
as well as main lane work on SH 121.
Utility relocation was part of the initial phase of construction,
including electric distribution and telecommunication lines.
"Probably our biggest challenge at that time was a 24-in.
water main that crossed the project at the Headquarters Drive
underpass," Bouma said. The main was eventually moved
approximately 600 ft. north of its original location with
no interruption of water service to local customers.
Additional Features
Once the project is completed, it will boast several new
design features recently adopted by the tollway authority
for its entire system.
"We just implemented system-wide design guidelines, and
this project will be the first to use those," Bouma said.
"We are working with Balfour Beatty to change-order a
lot of new design features into the project, and we believe
it will be a signature project for us."
The tollway extension will feature modified traffic rails
similar to TxDOT's new single-slope traffic barrier but will
have a modified back face. The tollway will also feature unique
steel railings on the underpass bridges and more architectural
finishes with its lighting designs.
"For example, on a normal bridge truss, we're going to
use large tubular steel cantilevers," Bouma said. "It
is also the first project that will feature our agency's new
signature look in toll plazas."
Scheduled for completion in 2004, the DNT extension will end
just north of SH 121. However, plans are already under way
to extend the tollway to U.S. Highway 380.
Construction on that extension is expected to begin next year.
| PROJECT
TEAM |
| CONSTRUCTION
MANAGER : |
Kellogg Brown &
Root, Houston |
| GENERAL
CONTRACTOR: |
Balfour Beatty Construction
Inc., Austin |
| PROGRAM
MANAGER: |
North Texas Tollway
Authority, Plano |
| LOCATION:
|
Frisco |
| OWNERS: |
North Texas Tollway
Authority, Plano; Texas Department of Transportation,
Austin |
|