UTSA
Using Design-Build System For New Academic Building
BFW Construction, HOK Teaming For $32 Million Project
By D.Ann Slayton Shiffler
With its classic Hill Country limestone façade and
a distinctive red clay tiled roof, the new Academic Building
III at the University of Texas campus in San Antonio sets
a new standard in usage and style at the growing university.
"The design team was challenged with designing this facility
in a new language that the University of Texas system has
been striving for," said Alan Colyer, vice president
and account manager for higher education for Kansas City,
Mo.-based HOK Architects Inc.
"(We are) sort of going back to the architectural character
of some of the buildings on the Austin campus and yet finding
a way to design it with some of the regional context of San
Antonio, and of course (fitting) with the previously constructed
buildings on the UTSA campus."
HOK designed the building and organized the design-build team
that is on target to complete the building by May. Temple-based
BFW Construction is the general contractor for the $32 million
project that also calls for the renovation of an existing
building on campus. The entire project is slated for completion
in spring 2005.
"The red clay tile roof and limestone set the stage for
future construction on the San Antonio campus," Colyer
said. "The building represents a new front door to the
campus because the new entry drive will lead right into this
building. My understanding is that UTSA is in a significant
building mode for onsite residential facilities, and I see
the campus taking on a new flavor."
In mid-July, the cast-in-place, 204,000-sq.-ft. academic building
was about 50 percent complete. With an L-shaped footprint,
the building will feature two wings: one with four stories
and the other with five, with the wings connected at the second
floor. From some angles the structure appears as two separate
buildings.
A particular challenge of the design team was to create a
building that would accommodate many different uses, Colyer
said. The building will house classrooms, small auditoriums,
computer laboratories and student services departments, including
financial aid offices. The administrative suite for the university
president and the regent's board meeting room will also be
in the new structure.
The building will feature the latest technologies in wiring
and wireless communications.
"It's going to have some sophisticated infrastructure
involved, but most university buildings demand that today,"
Colyer said.
Construction Continues
While the design team was put in place a year prior to construction,
ground was not broken until September 2002.
"The concrete structure is poured out and we are finishing
the stud columns for the roof," Bob Evans, resident construction
manager for the University of Texas System, said in early
July. "We're probably a little ahead of schedule. It's
actually going well.
We're meeting expectations."
The concrete framework and basement required about 5,700 cu.
yds. of concrete, all of which was poured in place.
The steel frame for the red-tiled roof is being fabricated
on the ground in several sections that was to be lifted into
place over the summer.
Since the project began, two cranes have done the lion's share
of work - a 50-ton crawler crane owned and operated by Texas
Crane Services of San Antonio and a tower crane owned by Dallas-based
Lewis Equipment Co.
One of the most challenging aspects of construction was the
basement, which required excavation to between 20 ft. and
25 ft.
"There was a lot of rock busting involved," said
BFW project manager Joel Benjergerdes, who added that the
building's mechanical systems will be housed in the basement.
Aside from dealing with the rock, the construction team ran
into a cavern soon after the basement excavation began.
"Because we are on the Edwards Aquifer, there are recharge
features," Evans said. "It was not an active cavern,
but once we penetrated it we had to get the environmental
agencies in to come and take a look. We had to follow the
protocol in that situation.
There are rules that are engaged when you run into something
like this - it's unusual to run into one."
The cavern didn't present any issues, but it changed the sequence
of work, Evans added.
Benjergerdes said his crews will work to get the building
enclosed by early fall. The cut limestone is being pieced
together using the Arriscraft system.
Evans and Benjergerdes said there have been no major hiccups
thus far, but working in such a tight space hasn't been easy.
"We don't have the luxury of a big open field to store
materials," Benjergerdes said.. "It's a challenge
but again has not caused any limitations."
Once the building is complete and tenants move in, the construction
team will begin renovating the vacated space on the fourth
floor of the adjacent library. The design work for that stage
of the project is nearly complete, Colyer said.
"Much of the vacated space in the library will be renovated
for new usage," he added. "The library will be able
to expand into those spaces."
Design-Build Praised
The design-build delivery system has allowed the San Antonio
project to progress smoothly.
"Design-build works well for this type of project,"
Benjergerdes said. "It has its challenges because of
the amount of paperwork, but it has still worked well."
Colyer said the UT System has embraced the design-build method
over the past few years for its building projects on several
campuses, although more recently has gone back to more traditional
methods.
"For the success of a project like this, and developing
it in a design-build process, you need all the entities to
work in an environment of trust," he said. "Fortunately,
we had worked with BFW on a similar project in Harlingen for
UT. The lines of communication were open and the relationship
was in place and the lines of trust were there. It's been
a pretty smooth design process that ultimately transitioned
into construction."
UT's Evans said he sees value in both the design-build process
and the competitive bid process.
"We use design-build quite a bit," he said. "This
is the second time I've been involved with it. There are advantages
of design-build and advantages of other processes. On this
job, design-build has worked well."
| PROJECT
TEAM |
| GENERAL
CONTRACTOR : |
BFW Construction Inc.,
Temple |
| OWNER: |
The University of Texas
System, Austin |
| LOCATION: |
San Antonio |
| ARCHITECT:
|
HOK Architects Inc.,
Kansas City, Mo. |
| STRUCTURAL/CIVIL
ENGINEER: |
Jaster-Quintanilla Consulting
Engineers, San Antonio |
| MEP
ENGINEER: |
RB Tarrillion and Associates
Inc., San Antonio |
| TELECOM/VOICE/DATA
ENGINEER: |
OTM Engineering, Austin |
| INTERIOR
DESIGN/LANDSCAPE ARCHITECT: |
Ford, Powell & Carson,
Architects and Planners Inc., San Antonio |
|