Features
 Current Features
 Past Features






Features - November 2003
Teamwork Builds DFW's Terminal D
Structure of $1 billion terminal building now substantially complete

Construction on Dallas / Fort Worth International Airport's $1.07 billion Terminal D, which began in 2000 but was in planning stages years before that, is substantially complete.

In September, work continued on skin, roofing and dry-in activities. Crews were working on the parking garage structure and starting the skin. Roadways remained in structural stages.

advertisement


"The Airport Development Team is the biggest success," said Tom Skinner, project manager for the Terminal D program for managing general contractor Austin Commercial of Dallas. "The pure massiveness of trying to coordinate a terminal program, a roadway system, an upgrade to a central utility plant and a hotel that's imbedded in a terminal has been the biggest challenge we have had."

The development team, established in 1990, included more than 53 architectural and engineering firms. Corgan Associates, Dallas, is the architect of record. HKS Inc. serves as the lead managing architect. HNTB Corp. was involved in the design process. All are based in Dallas.

Austin received a negotiated guaranteed maximum price contract for the Terminal D program. Value engineering has continued throughout the project.

"We were integrated and working together, looking at construction methods, materials, sequencing of the work," and from early on, said Clay Paslay, executive vice president for airport development at DFW.

Paslay said the project remains on target for its original completion date in 2005 and within its original budget.

The fast track, design-build Terminal D project includes a 2 million-sq.-ft. terminal, an 8,100-space parking facility, three levels of roadways and related ramps. The terminal is a hybrid structure with cast-in-place concrete and structural steel. It has a federal inspection facility capable of processing 2,800 international passengers per hour.

The structure has seven levels divided by activities and 23 swing gates able to handle wide- or narrow-body aircraft.

In addition, Austin is integrating a 298-room Grand Hyatt hotel into the structure. The $58.4 million hotel project received separate funding.

DFW Airport will own the 12-level hotel, and Hyatt Hotels Corp. of Chicago will manage it. Rooms will rise above the terminal with a ballroom and meeting space below it. The ceilings in the basement level are 19 ft. high, with a large clear span.

Austin put together designated work groups for each aspect of the terminal project.
The groups meet weekly, and a representative from each meets with upper management. All key decision makers - contractors, owner and major subcontractors - are located in a field office at the airport.

DFW Airport invested in a communication network and common software for budgeting, scheduling and project management and other tasks.

"There was a lot of upfront planning and upfront investment made to create a project management that kept everybody co-located and on the same communication platforms," Paslay said. "Everyone has been on the same sheet of music, if you will.
And that has helped dramatically as we move forward through this process."

Before starting construction, the development team investigated and put in place logistical and operational systems to manage the program with minimal disruption of airport operations. The airport established a roadway management plan to keep people accessing the existing terminals separate from construction activities.

Due to concerns about hydrocarbons associated with jet fuels polluting the environment, DFW Airport established >> a soil-testing program. Any dirt removed is checked, inventoried and tracked. Depending on readings, the soil may be sent for treatment or reuse.

Austin built a major underground storm-drain system to handle water. The 90- to 130-in pipe tunnels for a couple of miles underneath taxiways and adjacent to runways.
Crews use manhole locations to push pipe into place between the manholes.

Terminal D construction was under way when the Sept. 11, 2001, terrorism attacks occurred, and afterwards designers made substantial structural and system changes.

"Austin and its team did a yeoman's job of integrating those structural design changes in the midst of construction," Paslay said. "It does impact your flow of work and packaging strategy, but it has been fluid enough and dynamic enough that we were able to accommodate those changes without too much of an impact to the project."

About 1,700 craftspeople and 350 administrative people work onsite daily. Austin has more than 200 subcontractors.

Airport officials instituted many unique programs to facilitate on-time completion of the enormous undertaking. The owner purchased insurance for the entire program, including professional service insurance, and saved money by rolling coverage for all of the projects together.

Everyone entering the site must complete a 40-hr. session that includes first aid and learning English and Spanish words for basic construction terminology.

"It was a conscious investment on our part, but I think we are seeing great dividends," Paslay said. "Our lost-time ratio to date is 0.5 versus a national average of 3.9. Small and emerging contractors, who do not have the where-withal to develop safety training programs of that nature, are now exposed to world-class training."

A subcontractor working at a different Austin project saved a co-worker's life by quickly starting to perform cardiopulmonary resuscitation he learned during a DFW training session.

Paslay said he expects some of the unique elements implemented on this job will be incorporated by other governmental aviation entities as major U.S. airports move forward with expansions.


 Click here for more Features >>



 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved