Features
 Current Features
 Past Features






Features - November 2003
Blast Resistant Design to Protect Airport Terminal
Killeen Airport terminal is among the first to be designed after September 11, 2001

By D.Ann Slayton Shiffler

Built with approximately 1,000 tons of structural steel and 9,500 cubic yards of concrete, the new Ted C. Connell Terminal Building at Gray Army Airfield in Killeen will be among the first airport terminals in the country designed to be blast resistant. The building was engineered to withstand a bomb blast from the parking lot.

The $30 million facility will also feature a "resolution room," hardened space within the terminal building that was designed to be used to detonate any explosive devices found during the luggage screening process.

advertisement


Among the first airport terminals to be designed after the terrorist attacks of September 11th, the facility features a number of other interesting design attributes. A joint project of the City of Killeen and the Fort Hood military base, the airport will be one of the few joint-use public/military airports in the country.

Carter & Burgess' Fort Worth office, the architect and engineer on the project, finished an enormous amount of design, redesign and engineering work prior to ground breaking. Austin's Constructors & Associates Inc. began construction of the terminal building in January 2002.

As a result of the terrorist attacks on 9/11, the terminal's design was totally reexamined. In fact, the design process was about 80 percent complete when the terrorist attacks took place. The Carter & Burgess design team reworked the design to meet a number of criteria, specifically being able to deal with a bomb blast and related terrorist threats.

"There was a major redesign effort on the building after the September 11th attacks," said Jeff Toner, program manager for the project for Carter & Burgess. "We were concerned about many things, like how far the parking lot could be from the terminal building.

"We did blast analysis to determine how it (the terminal building) would withstand bomb blasts at different distances."

The blast data allowed the design team to identify how much to reinforce the building.

"We needed to build a building that wouldn't have a catastrophic collapse," says Toner. "Once we had the results from our analysis, we realized we would need bigger structural steel members. We are using a lot of precast concrete to harden the building. The glass used on the exterior of the building is blast resistant to mitigate the effects of a blast for people inside."

Constructing this building has required an inordinate amount of teamwork between not only the construction teams but also the City of Killeen, which is considered the developer, and with the military, which is considered the owner.

The city of Killeen entered into a lease with Fort Hood for the terminal which will serve as a passenger commercial airport. A joint management board was formed between the city, the military and the construction teams to assure that the construction effort runs seamlessly.

Bob Albanese, president of Constructors and Associates, said that teamwork has been critical because of all the sensitive entities involved.

"There's much more security on the site," he says. "Because the military monitors our security systems, there is some additional infrastructure. There are additional cameras and security processes. We want to be a good neighbor to the military and we have worked with them as best we could."

Scott Lewis, project manager for Constructors, said the job has been progressing quite well, even though the security level is higher than that at most jobs.

"We heave security fences that separate us from the military and we do have work that is on the military side of the fence," says Lewis. "We have security badges for all our workers and we have to provide the names of the individuals who will be on the military property. We have a guard at the entrance to the gate. It's not a come as you please site."

The three-story structure will comprise about 83,000 square feet. All three stories are above ground, with the first floor as a baggage handling area. The building's electrical and communications rooms will also be located on the first floor. The second floor is a food court and also includes the main concourses for aircraft boarding with four gates and room for expansion. With just 5,000 square feet of space for administrative offices, the third floor has a smaller footprint than the second and first floors.

The site was already cleared when Lewis' crews arrived. Primary water lines and utilities were in place as well. The building is structural steel with pre-cast concrete skin. The foundation was poured slab on grade beams over drilled piers.

"We are about 80 percent complete with structural steel erection and about 30 percent complete with precast erection and we have started all of the mechanical, electrical and plumbing rough in work," says Lewis in mid September. "We've completed all the blast window design and fabrication is starting on that."

Stone veneer panels will be installed over some of the precast panels in the building.
The design features an impressive barrel vaulted roof.

At this point, Lewis said the project has not had any delays, although there have been some design changes. The building is on target to be completed by the third quarter of 2004.

"We've had some changes in scope to deal with," he said. "But I don't think these things will affect our completion date."

By mid September, Lewis said that there were between 80 to 110 workers on site on a given day, depending on the various stages of construction.

"We probably will be getting up to 200 to 250 workers when the finishes start going in the building," Lewis says.

Aside from the contract to construct the terminal building, Constructors and Associates will also be building the apron and taxi way as well as the land side improvements around the airport as well as the parking areas, maintenance, fueling areas, rental car areas and storm water retention areas.

A licensed architect, Lewis said the building's design is quite impressive, as are the blast resistant materials.

The structure is a lot heaver than it normally would have been," he says. "The precast panels are very thick. The window glazing and frames and glass itself are all structural. The glass in some areas is over an inch thick and it's double glazed. All of the mechanical, electrical and equipment and ceilings have additional bracing that goes into them so that they wouldn't fall in the event of a bomb blast.

"It's almost a true bomb shelter," he continues. "I know where I'm going if we have a disaster."

The "resolution room" within the terminal was designed for "suspect" materials that might be discovered during the baggage scanning process.

"It's a concrete room with an 18 inch thick wall and a blast door," Lewis says. "It's basically designed specifically for a piece of luggage with a bomb in it."

For the most part, Toner said the extreme blast analysis efforts that went into the eventual design of the building was so that they could get the parking areas as close to the building as possible.

"When airports go to heightened security they lose a lot of their parking facilities," he explained. "We didn't want it to happen that when the terminal opened the government would then say 'guess what, you can't use the parking in front of the building.' Parking is a big source of revenue. We just wanted to be proactive in our deign and provide a higher level of safety for the traveling public."

While Carter & Burgess has had experience designing blast resistant buildings for the military, this project was different because in most cases the military will provide the exact criteria.

In some cases, seismic materials and designs were replicated because there is so little true bomb blast design criteria.

Albanese is very impressed with the level of cooperation that his company has experienced with this project.

"One of the great things is it is truly a joint effort," he said. "We're working with the city of Killeen, the FAA, TXDOT, Carter & Burgess and all the sub contractors. The FAA provided most of the funding for the project. The military provided the land. It was a joint effort on a lot of different agencies to make this project happen. The cooperation is remarkable."

He said his company was very proud to get this job, which has been very high profile and very interesting to construct.

"Constructors was very pleased and excited to win this project from the City of Killeen," he says. "The aviation sector is one of importance to our company and we intend to pursue many other projects similar to the Ted C. Connell Terminal Building. The City of Killeen representatives, as well as the architectural and engineering team of Carter Burgess, have been excellent to work with thus far. Although this project was awarded to us on a "low bid" basis, we believe the "team building" concept is the approach all parties are engaged in. We look upon the City of Killeen as a Client and will keep that attitude throughout the duration of the project."

PROJECT TEAM
GENERAL CONTRACTOR: Constructors and Associates
ARCHITECT/DESIGN: Carter & Burgess, Transportation Program Group, Aviation Group, Fort Worth
OWNER: City of Kileen; U.S. Army, Fort Hood

 

OTHER SUBS
Mechanical & Plumbing Airco Mechanical, Austin, TX
Structural Steel Alamo Steel Co., Waco, TX
Sealants & Waterproofing Armor Sealants & Firestopping, Round Rock, TX
Exterior & Interior Signage Austin Architectural Graphics, Austin, TX
Fire Proofing Bahl Fireproofing, Round Rock, TX
Precast Concrete Erection & Steel Erection Bosworth Steel Erectors, Dallas, TX
Cast-in-Place Concrete C.J.'s Concrete Construction, Gatesville, TX
Standing seam Roof & TPO Roof CEI Roofing, Inc., Dallas, TX
Exterior Aluminum Sunscreens & Interior Aluminum Canopies Childress Metals, Arlington, TX
Millwork D3, Inc., , Lorian, OH
Passenger
Boarding Bridges
DEW Engineering & Development Ottawa, Ontario, Canada
Fire Sprinkler System Honeycutt Fire Systems, Pflugerville, TX
Doors & Hardware Horizon Hardware, Austin, TX
Electrical Jo Luis Corporation, Killeen, TX
Metal Studs, Drywall & Acoustical Ceilings Lasco Drywall, Round Rock, TX
Baggage Handling System Logan Fabricom, Inc., Louisville, KY
Architectural Precast Concrete Meridian Precast & Granite, Inc., Waco, TX
Architectural Louvers & Walk-off Mats Metroplex Architectural Products, Dallas, TX
Landscaping & Irrigation Muhl Landscaping, Waco, TX
Terrazzo National Terrazo Tile & Marble, Inc. Houston, TX
Fall Protection Pro-Bel, , Ajax, Ontario, Canada
Masonry Quality Brickworks, Waco, TX
Elevators & Escalators Schindler Elevator, Austin, TX
Earthwork Shallow Ford, Temple, TX
Site Utilities Shelton & Shelton Plumbing, Killeen, TX
Mufids/Bids Com-Net, , Miamisburg, OH
Painting Systems Painters, New Ulm, TX
Glass & Glazing Tepco Contract Glazing, Inc., Dallas, TX
Kitchen Equipment Trinity Restaurant Equipment, Arlington, TX
LANDSIDE IMPROVEMENTS & STRIPING
Pre-Engineered Buildings Aycock Construction, Inc., Harker Heights, TX
Cast-in-Place Concrete C.J.'s Concrete Construction, Gatesville, TX
Electrical Jo Luis Corporation (Electrical), Killeen, TX
Earthwork Shallow Ford (Earthwork), Temple, TX
Site Utilities & Plumbing Shelton & Shelton Plumbing, Killeen, TX
Fuel Storage Systems Unified Services of Texas, Inc. San Antonio, TX
Parking Control Systems Vehicle Access Control, Inc., Dallas, TX
Asphalt Paving

Wheeler Coatings Asphalt, Inc. Round Rock, TX


 Click here for more Features >>



 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved