|
Ceco Concrete Construction
The Promise of Delivery Set in
Stone
By Angelle Bergeron
Ceco Concrete Construction, the largest formwork subcontractor
in the country, was founded in 1912 by C. Louis Meyer and
has been continually operating in Texas since the 1930s.
Meyer developed the concept of reusable steelforms for site-cast,
one-way joist systems, which lead to the company's initial
success and eventually became an industry standard. But it's
Ceco's straightforward delivery that secured the company's
position at the top.
"We do what we say we are going to do," said Mick
Haggerty, who heads the San Antonio office of the Kansas City,
Mo.-based firm. "And we do it on time, within budget
and per our customers' requirements."
Each year, Ceco's engineers, forming specialists, project
managers and trained field crews build more than 200 projects
representing more than 20 million gross sq. ft. That experience
is invaluable to customers, Haggerty said.
Ceco recently completed the Baylor University Sciences building
with Beck Construction Group. The project was one of several
that Ceco has completed in its long-term relationship with
Baylor and featured 600,000 sq. ft. of one-way wide-module
joist system.
In another project, the company worked with SpawGlass Construction
Co. to complete the Valero Corporate Headquarters in San Antonio.
The project included 660,000 sq. ft. of one-way wide-module
construction in multiple buildings.
One-way wide-module joist construction reduces the amount
of rebar and concrete required, resulting in reduced cost
and faster delivery, Haggerty said. Although the method has
become commonplace in construction, Ceco boasts one of the
largest inventories of forms in the country.
"Nobody in Texas has a larger or more complete inventory
than we do, from standard plyforms and steelforms to custom
fiberglass and aluminum," Haggerty added. "We have
the capability to perform on just about any job that is out
there. I think that is our niche. The bigger the job, the
more demanding the schedule and the more complex, the more
qualified we are to do it."
Ceco has gained a reputation in the industry for tackling
technical projects such as the Texas Instruments building
in Dallas and the Motorola building in Austin. Both required
building clean rooms, which must carry heavy loads and provide
for continuous airflow between floors, Haggerty said. "Those
jobs required custom forms that provide a two-way joist system
with penetrations in the topping slab for airflow," he
added.
Ceco also worked with Fulton/Coastcon Construction on the
new indoor arena in Corpus Christi, scheduled to open in the
fall. The 500,000-sq.-ft. structure included exposed one-way
wide-module joists, poured-in-place raker beams and an elevated
ice slab.
Currently under way in Houston at the George Bush International
Airport's new parking garage, Ceco is utilizing a steel-beam
form system to meet demanding schedule requirements and is
particularly proud of the innovative forming system developed
for a double-helix ramp. The eight-level, 1-million-sq.-ft.,
poured-in-place concrete garage will accommodate 2,500 cars
and includes arrival- and departure-level roadways. "The
challenges of a tight international airport site with various
phasing milestones required close coordination with our customer,
Manhattan Construction Co.," Haggerty said.
Ceco is working with Vaughn Construction on the Harris County
Civil Justice Center in Houston. The 19-level structure will
contain 750,000 sq. ft. of concrete, utilizing one-way wide-module
joist construction.
While industry standards are constantly changing, Ceco manages
to maintain its cutting-edge position with new developments.
Originally, reusable steelforms were developed for one-way
joists at 2 to 3 ft. modules, Haggerty said. Today's forms
have evolved into 5- and 6 ft.-wide modules.
"Fire codes evolved, the required topping slab got thicker
and, as that happened, we were able to spread the joists out
farther apart," he said. That too, has become an industry
standard.
Ceco has maintained the highest safety standards in the industry,
recently achieving 1.8 million safe person hours, without
a lost time accident. "That's a pretty big achievement,"
Haggerty said. "Especially considering the relative dangers
in our industry, our scope of work, which is constantly exposed
to weather or a fall, is labor intensive and involves heavy
lifting."
The company's lost workday case incident rate is 50 percent
below the industry average, allowing Ceco to slash two-thirds
off worker's compensation and general liability costs, Haggerty
said.
Moreover, Ceco's commitment to safety is another way the
company has retained its position in the industry. "We
partnered with OSHA, when the organization was in its infancy,
to work towards 100 percent fall protection," Haggerty
said. "We were the first company to implement leading-edge
fall-protection systems."
In 1989 the company introduced a spool system, fashioned
after fishing tackle, which is used on the leading-edge level
of projects.
The company says another one of its goals is to be the preferred
employer in the industry. One way to accomplish that is to
reduce the amount of effort required by employees to perform
tasks, which includes switching to all-aluminum systems, more
motorized material handling equipment and the latest generation
of shoring components.
"We have invested millions of dollars in new forming
systems that are lighter and more efficient in an effort to
reduce strain on our employees while improving efficiency
and safety," Haggerty said. "All these things put
our field crews in a better position to do what we say we
are going to do and accommodate our customers' requirements
and meet their goals."
The current trend in steel pricing has increased the popularity
of cast-in-place concrete buildings. "With steel prices
the way they are, concrete buildings are definitely the way
to go," Haggerty said.
|