|
Changes Ahead for Dallas' Light Rail
DART Working to Stay on Track
By Lesley
Hensell
Gridlock is a word all too familiar to
Dallas-area commuters. The word is also the impetus behind
the $2.5 billion expansion of Dallas Area Rapid Transit's
light-rail system.
But the larger the light-rail system
becomes, and the more construction that is planned, the more
DART risks becoming mired in gridlock of its own. DART has
developed decades-long timelines and multibillion-dollar budgets
for its planned expansion, which will nearly double the system's
miles of track. And it will take more than a little time and
money to get DART to its destination.
As problems began cropping up in the
first phase of DART's Northwest Corridor expansion, one of
two major projects on tap, DART moved quickly to change its
construction management process.
Miles and Miles
DART's planned
expansion includes two major lines. The first, the Northwest
Corridor, will run 23 mi. over two branches and will include
19 stations. The first branch will be an extension from the
West End Station in Downtown Dallas, heading north along Harry
Hines Boulevard on the former path of the Union Pacific Railroad,
through Dallas and Farmers Branch to Frankfort Road in Carrollton.
The second branch
will extend from the planned Bachman Station in Northwest
Dallas to Las Colinas in Irving and, finally, to Dallas-Fort
Worth International Airport. Segments of the $1.5 billion
project will begin opening about 2010, said Morgan Lyons,
spokesman for DART.
At the same time,
the 10-mi., $1 billion Southeast Corridor rail line will be
built out to connect the Pleasant Grove area of Dallas with
the existing Pearl Station downtown. This contract will include
a 2.3-mi. section of the Northwest Corridor. The Southeast
extension is expected to be complete in 2013.
"We anticipate
that by fall or winter of next year, the dirt will be flying
and we should be moving in a positive direction," said
Timothy McKay, senior vice president of project management
for DART.
Victory at Last
The first segment of the Northwest Corridor recently reached
substantial completion. It runs from West End Station to Victory
Station, which serves American Airlines Center. The $26 million
project launched in June 2002 and was originally scheduled
for completion in January 2004.
Just 1.7 mi. in length, the segment offers a case study
into the challenges of light-rail construction. It also presents
the real possibility that DART's 10-year construction goals
may well be a fantasy.
The project was planned in detail far in advance, with six
key milestones tied to different geographic locations of the
track, said Kurt Grier, project manager for Martin K. Eby
Construction, the contractor on the segment. Eby handled the
project from its Bedford office.
"The problem with this kind of project is that it's
a very linear process," Grier said. "It's hard to
gain days when you run into weather or mandated change orders
by the owner. On most jobs, you can figure out ways to go
down two paths at once to trim the schedule. But not on this."
When bidding out the project, DART said that the contractor
would be constructing the guideway on medium clay. And Martin
K. Eby based its bid on that information, Grier said.
"This was anything but medium clay we were working on,"
he added. "We found rebar in gigantic wads wound up like
spaghetti. We hit a foundation the size of a car. And we found
bathtubs, gravel and uncompacted soil."
Grier suspects that a portion of the construction site used
to be an old rail switchyard, while another area may have
been a dump.
"At one site, we were drilling in anchors and hit a
void," he said. "We were never able to retrieve
our screw. And this was under the existing guideway. We ran
into so much material that was not as noted on the geotechnical
reports."
Each time the team faced unusual conditions under the ground,
the project came to a halt.
"We had to put the owner on notice and go back to the
engineers for a redesign," Grier said. "Sometimes
we had to totally excavate to the depth of a pier and backfill
with decent dirt. Or we had to change to a footing-and-column
foundation instead of a pier. It totally changed the design
of the structure."
Another challenge was the continual flow of train traffic
through the worksite. About 70 trains a day, including commercial
haulers and the diesel commuter Trinity Railway Express, flew
through the jobsite each day at speeds of up to 60 miles per
hour, Grier said.
"We would have to shut down work before they were allowed
to pass through the jobsite," he added. "All crews
had to get 25 ft. or more away from the tracks. At the project's
peak, we had 150 people onsite. And considering most of it
was track work and guideway work, most people were within
the foul zone.
"When you've got 150 men sitting on their butts waiting
for a train to go by, you run through money really fast."
Between delays and exceptions, Martin K. Eby went far over
budget. Currently, project managers are creating exception
reports to submit to DART.
"Even if you run into change orders during construction,
you have to move on with the project and negotiate at a later
date," Grier said. "That's what we're doing right
now."
A New Approach
These challenges are one reason DART is adopting a new construction
process for the next phases of the project. Rather than hiring
a contractor at the outset of construction, DART will bring
a construction-manager/general-contractor-at-risk on board
during the design process.
"In prior phases, we would give the contractors a set
of 1,800 drawings and two big volumes of spec books,"
McKay said. "Then we would say, 'You've got 45 days to
give us a firm price.' There were some very good contractors
who could do that, but it didn't work really well."
By bringing on a CM/GC during the preliminary engineering
stage, DART hopes to eliminate the number of changes and obstacles
that arise during construction.
"We want to bring the contractor in early to work with
the design team and get him acclimated to the project,"
McKay said. "That way, we'll establish a true partnership
upfront. If we spend a little more effort up front, we hope
that once we start building we can eliminate changes and arguments
over pricing."
The GM/GC, which will be chosen some time this fall, will
be given a guaranteed maximum price. "This is kind of
like cost-plus, but with a ceiling," McKay said.
To choose the GM/GC, DART will take a best-value approach,
he said. Each bidder will be evaluated on three criteria:
technical abilities, including the project approach and game
plan for execution; past performance, determined by questionnaires
sent to reference organizations; and price, including reasonableness
and completeness.
"We're not necessarily going for the lowest bidder,"
McKay said. "We want to negotiate the best-value contract
using a competitive solicitation process to get there."
When DART first began operating its light-rail service in
1996, it was on time and on budget, Lyons said. The first
expansion opened under budget and six months ahead of schedule,
he added.
"We're used to having very aggressive and challenging
construction schedules," he said. "But we want to
do even better."
|