|
A Sound System
Grand Facilities on Canyon's Horizon
In the heart of the Texas Panhandle 12
mi. south of Amarillo, the new 146,000-sq.-ft. Fine Arts Complex
at West Texas A&M University in Canyon is expanding the
school's performance spaces. The adjacent Mary Moody Northen
Hall is also getting an 18,000-sq.-ft. addition.
The new complex also includes classrooms, offices and practice
rooms and support facilities such as costume and scene shops
in the building's basement. The $23 million project is more
than 25 percent complete with delivery scheduled for August.
The complex is a structural-steel-and-poured concrete structure
with a tapered rubber roof system. "The actual construction
of it is not a difficult building to put together other than
much of it being structural concrete and the additional forming
for that," said Martin Tickle, project manager for Lee
Lewis Construction Inc. of Lubbock the project's general contractor.
The exterior is clad with a combination of brick and stone.
Principal architect Bill Smith of Rees Associates Inc. of
Dallas said the prevalent palette of materials on campus helped
provide ideas for the look of the building. "It sits
right there at Palo Duro Canyon, so we actually used stone
as a metaphor for the walls of the canyon," Smith said.
"There's a large stone wall that runs from outside the
building at the entry and knifes through and becomes the focus
wall in the lobby that serves all the performance venues."
Those venues include a proscenium stage theater with fly
loft, a recital hall and a flexible black-box theater space.
"When you make those spaces adjacent to one another like
we did, you've got some extra work to do in the walls that
separate them to make sure that if you have multiple performances
going on in several venues, you're not having sound going
from one to another," Smith said.
Thick concrete-masonry-unit slabs with sound absorbing walls
on either side address that concern.
Even more critical on the sonic front is preventing noise
from the mechanical systems from entering the theaters. "The
cu. ft. per minute of air comes into the theaters at a very
slow speed, so that you don't hear airborne noise," Smith
said. "And there are special efforts in the ductwork,
both supply and return, so that you don't pick up the machine
noise."
He said that the machine rooms are isolated and have sufficiently
thick slabs so that they don't transmit vibrations from the
air handlers-which are low frequency-into the structure. The
air-handling system is also zoned to prevent "airborne
noise that could come from a practice room into the performance
venues," Smith added.
Insulated sound-isolation floors on a jack system help with
sound issues in some of the rooms in the complex. "The
floor sits on neoprene sound-isolation pads and jacks up,"
Tickle said. "You pour the depression slab first. Then
you go in and set the jack system. Then you go back in and
pour the topping slab over it.
"Once the topping slab is cured, then you come in and
jack the floor up. It creates a gap between the depression
slab and the sound-isolation slab. It stops the sound from
migrating into the slab and transferring into other rooms."
Smith said another problem that had to be dealt with was
a railroad track not far away. "There's some work done
to insulate and isolate any noises that would be coming from
the occasional train," he said.
With the theater space at the building's glassed-in front
adjoining a two-story stack of classrooms, offices, studios
and practice spaces, it's possible to lock down the lobby
for public performances and still have the rest of the building
accessible for students, Smith said.
After the design was completed, a value-engineering process
freed up $2 million to help accommodate the addition to Northen
Hall.
Interior wood species and the roofing material were changed
within the complex, and some interior limestone was replaced
by drywall. The feature wall extending outside the theater
lobby was reduced.
By the start of the fall semester, the structural steel
frame was coming out of the ground and the project was proceeding
on schedule.
Since the institution became a part of the Texas A&M
system after the 1991-92 legislative session, it has positioned
itself as the fine-arts magnet within the system. "It's
a long-overdue facility for the campus," said Deborah
Hardt, architectural project manager for the Texas A&M
System. "They'll have an excellent calling card to bring
students there who are interested in that curriculum."
Owner: Texas A&M System,
College Station
General Contractor: Lee
Lewis Construction Inc., Lubbock
Architect: Rees Associates
Inc., Dallas
Structural Engineer: Jaster
Quintanilla, Dallas
|