|
Best of 2005
Health Care
M.D. Anderson Cancer Center, Ambulatory Clinical Building
Submitted by: Hensel Phelps Construction Co., Austin
Location: Houston
Key Players:
Owner: The University of Texas System, Austin
General Construction: Hensel Phelps Construction Co., Austin
Architect of Record: FKP Architects Inc., Houston
Signature Architect: Kaplan McLaughlin Diaz, New York
Civil/Structural/Parking and Traffic Engineer: Walter P. Moore
Engineers + Consultants, Houston
A design-build project, M.D. Anderson Cancer Center Ambulatory
Clinical Building, totaling 781,700 gross sq. ft., was designed
as the "signature" building on M.D. Anderson's site,
housing cutting-edge technologies within an environment of
spacious lounges and rooftop gardens utilizing natural lighting.
The building's lower five floors are built from 130,000 cu.
yds. of cast-in-place concrete, while the upper seven floors
are structural steel. The team decided to transition between
the two materials after examining ways to optimize the grid
for a parking garage and a first-class health-care building.
To meet M.D. Anderson's aggressive schedule, the team elected
to transfer the load from concrete to steel on level two,
as the building would be speedier to erect using structural
steel. Level two now features large concrete transfer girders
to accommodate the larger column spacing in the underground
parking garage.
Despite its cutting-edge technologies such as the digitized
diagnostic imaging equipment and high-energy linear accelerators,
the ACB was designed to be a soothing, comforting place for
wellness. The lobby is hotel-like, with commissioned art,
fountains and massive aquariums.
The underground parking garage maximizes greenspace for patient
enjoyment. The parking levels have uninterrupted ramps with
no parking, so patients on wheelchairs can travel on level
grades. Adequate vertical circulation points or elevator lobbies
minimize walking distances.
Valet parking stations were incorporated into the design
of the 963-car garage as well as the four lanes of passenger-side
patient dropoffs running through the building.
Higher Education/Research
SMU, James M. Collins Executive Education Center
Submitted by: Centex Construction Co.
Location: Dallas
Key Players:
Owner: Southern Methodist University, Dallas
Contraction Manager: Centex Construction Co., Dallas
Architect: The Hillier Group, Dallas
Structural Engineer: Thorton-Thomasetti Group Inc. Engineers
Division, Dallas
MEP Engineer: ccrd partners, Dallas
Southern Methodist University supports six degree-granting
schools, including the Cox School of Business. The James M.
Collins Executive Center is the school's newest asset.
The Collins Executive Education Center enables the SMU Cox
School of Business to expand its programs, enrich the educational
experience for all students and ultimately enhance its national
and international reputation as a top-tier business school.
Centex Construction was selected to build the center in 2003.
The Collins Executive Center is Centex's seventh project on
the SMU campus in the past 18 years.
The center is located immediately east of the Cox School
of Business. The Hillier Group designed the Collins Center
to be a 50,000-sq.-ft., self-contained teaching and conference
facility housing the Cox School's Executive and Management
Development and affiliated programs, as well as to provide
office and classroom space for the executive MBA program.
Design features in the center are in keeping with the campus'
traditional Georgian architectural theme.
Included in the building are a 300-seat auditorium, 5,000-sq.-ft.
three-story commons area, kitchen area and dining room with
seating for 120. There also is a business center, as well
as executive lounge, numerous faculty offices and oversized
workrooms.
An outdoor plaza on the north side of the building offers
additional event space, and a rooftop terrace provides an
environment for networking. The academic areas are equipped
with the latest technology to support a variety of instructional
techniques to include four-tiered classrooms with seating
for 66 students, a 40-seat classroom with flexible seating
arrangements, 15 breakout rooms with seating for groups of
six to 10, boardroom with seating for 24, conference room
with seating for 12 and two uniquely shaped seminar rooms
overhanging the three-story commons area.
Industrial
Emergency Power Reconfiguration
Submitted by: Linbeck Construction Group LLC, Houston
Location: Houston
Key Players:
Owner: St. Luke's Episcopal Health System
General Contractor: Linbeck Construction, Houston
Architect: RTKL Associates, Dallas
Electrical Engineer: Burns DeLatte & McCoy Inc., Houston
Electrical Contractor: Fisk Electric Co., Houston
Mechanical Contractor: Gowan Inc., Houston
St. Luke's Episcopal Hospital was completely "blacked
out" by Tropical Storm Allison in June 2001 when 8 ft.
of water surged into the hospital's basement where the power
systems were housed.
Similar scenarios played out in facilities throughout the
Texas Medical Center. The flooding at St. Luke's damaged most
of the main switchgear, transformers and many automatic transfer
switches. The emergency power generators were located .25
mi. from the hospital, and the underground cables connecting
the power source to the hospital were compromised because
the flood waters damaged the feeder lines.
Both the normal and emergency power systems were temporarily
repaired within 11 days. All other hospitals ravaged by Allison's
flood waters required a minimum of 30 days to get back up
and running.
Permanently repairing the emergency power system at St. Luke's
was the epitome of precision planning. TeamBuild, a collaborative
team process developed by Linbeck, was the process that made
it possible to transfer thousands of circuits, raze and rebuild
several hospital floors and install millions of dollars worth
of equipment without impacting hospital operations.
The process was embraced by the hospital engineers and administrators,
architects, engineers and subcontractors.
Linbeck has been using the TeamBuild process since 1968
because it has proven it works every time. It brings all key
team members into the decision-making process from the beginning
- including client representatives, facility users, owners,
developers, architects, engineers, constructors and subconsultants.
TeamBuild first outlines the client's needs, and then the
team members work collaboratively to develop a gameplan that
best serves those needs.
The plan is reviewed and refined through every phase and
subphase of the project.
K-12
Burnet High School
Submitted by: American Constructors, Austin
Location: Burnet
Key Players:
Owner: Burnet Consolidated ISD
Architect: Fromberg Associates Inc., Austin
General Contractor: American Constructors LLP, Austin
Structural Engineer: LOC Constultants, Austin
Civil Engineer: LNV Engineering Inc., Corpus Christi
MEP Engineer: Kent Consulting Engineers, Austin
The project consists of six buildings totaling more than
250,000 sq. ft. constructed on a site covering more than 75
acres.
The buildings, predominately slab-on-grade with site-cast,
tiltup walls, contain classrooms, administrative areas, kitchen
and cafeteria, courtyard amphitheater, visual performing arts
area, 960-seat auditorium, 1,400-seat gymnasium and more.
The roof systems are architectural standing-seam metal and
modified bitumen for the low-sloping roofs.
Sitework includes complete landscaping and irrigation, a
water-quality pond, two athletic fields, parking, storm sewage
and more. Interior finishes include drywall, ceramic tile,
epoxy flooring and terrazzo.
A big task in the project was changing the entire building
system after the bond had been passed and funding was allocated.
During the planning phase, it was determined that the campus
would be made up of pre-engineered metal buildings with a
combination of brick veneer and metal wall panels as well
as standard metal roofing panels.
After the budget was set and the bond passed, American Constructors
convinced the Burnet CISD to upgrade the building system to
concrete tiltup walls with architectural standing-seam roofs.
Although the system provided a far superior product, it placed
severe strains on the budget.
During the entire design and construction process, American
Constructors worked to identify and implement value-engineering
items to reduce cost and provide the superior building system
while sill meeting the original budget.
Multifamily Residential
Buckingham Senior Living Community
Submitted by: SpawGlass, Houston
Location: Houston
Key Players:
Owner: The Buckingham, Houston
General Contractor: SpawGlass Construction Corp., Houston
Architect: Ambrose, McEnany & House, Houston
Architect (exterior):
Structural Engineer: Haynes Whaley Associates, Houston
MEP Engineer: Wylie & Associates, Houston
The Buckingham is a luxurious 464,000-sq.-ft., continuing-care
retirement community located along Houston's Buffalo Bayou.
The community consists of five main structures under one roof
and includes 205 one-, two- and three- bedroom independent-living
apartment homes; 60 skilled-nursing; 16 memory-support; and
43 assisted living units.
One challenge was constructing four buildings of different
structural components. SpawGlass discovered severe congestion
and elevation issues in many areas. The project team used
AutoCAD to overlay drawings and to compare elevations. MEP
coordination meetings were held regularly with four major
subcontractors and the architect.
Before the buy-out of the major subcontracts, material prices
on steel and wood products escalated to unprecedented levels.
The SpawGlass team hit the drawing board in an effort to help
offset the escalation costs.
There were plenty of obstacles during construction of the
unique four-story wood structure. Due the building's height
of 50 ft., the framing members were unusual, measuring as
large as 6 by 10 in.
With its proximity to the Gulf Coast, the project had to
be designed to meet 110-mph winds. The wind requirement compounded
by the building height and the owner's clear-space requirements
posed a challenge to the engineering of the building and in
its construction.
To the engineer, this meant plenty of structural wood shearwalls
and the use of the Simpson Strong-Tie Anchor Tiedown System.
As a solution, the framing subcontractor created a grid system
in AutoCAD that was then used as a tool to transfer the locations
onto batter boards and edge forms while a series of string
lines traversed the foundation in every direction.
The foundation resembled a spider web before each pour. In
the end, 1,000 ATS bolts were exactly where they needed to
be.
Private Building
Freescale Gown Room Relocation
Submitted by: DPR Construction Inc., Austin
Location: Austin
Key Players:
Owner: Freescale Semiconductor Inc., Austin
General Construction: DPR Construction Inc., Austin
Architect: PageSoutherlandPage, Austin
Civil Engineer: Baker-Aicklen Inc., Round Rock
Structural/MEP Engineer: Kinetics Systems Inc., Austin
This project involved the addition of a 2,200-sq.-ft., three-level
gown room attached to operating wafer-fabrication facilities
on two sides, with Class 10 clean room and Class 100 connecting
corridors.
The new Class 10 and Class 100 building was built between
and attached to two operating wafer-fabrication facilities.
For Freescale to maintain operations during the project, the
team had to ensure that in addition to creating a sterile
new addition, vibration and dust particulates from the construction
process did not affect adjacent buildings. The team followed
stringent semiconductor Clean Build Protocol, developed by
DPR through many years of projects within occupied clean facilities
to carefully monitor, measure and document each step of the
project.
Throughout the project, Freescale maintained 100 percent
of its operations. Aside from the necessary system tie-ins
for chilled water and the early smoke detection alarm, there
were no construction-related shutdowns.
To ensure minimal disruption to Freescale's business, DPR
coordinated the shutdowns two or three weeks ahead of time.
When necessary, DPR worked at night or on weekends to meet
the schedule and minimize disruption to business.
Soon after the start of preconstruction, Freescale requested
the already fast project schedule be shortened by four weeks.
The DPR team immediately ramped up coordination meetings with
the owner and architect to add schedule, procurement and constructability
input as designs were finalized.
The team broke the project down into three packages, broke
the packages into tasks and grouped the tasks into lists to
best meet the schedule. DPR's project superintendent became
the master scheduler in the field, coordinating each package
of work, overlapping trades and incorporating Freescale's
own facilities labor pool into the schedule.
Public Building
Tarrant County Family Law Center
Submitted by: Gilbane Building Co., Grapevine
Location: Fort Worth
Key Players:
Owner: Tarrant County
General Contractor: Gilbane Building Co., Grapevine
Design Architect: David M. Schwarz, Washington, D.C.
Architect of Record: GideonToal, Fort Worth Civil Consultant:
LOPEZGARCIA GROUP, Dallas Mechanical/Electrical Engineer: Summit
Consultants Inc., Fort Worth
Gilbane provided construction management services for the
new Tarrant County Family Law Center and Parking Garage. The
facility, solely dedicated to family courts and related functions,
consists of a five-story building totaling 258,541 sq. ft.
The facility includes a basement with equipment rooms, holding
cells for prisoners appearing in court and a secure parking
area for judges.
Phase one of the project was the construction of a 785-car
parking garage on the block to the west of the Family Law
Center. This project began in September 2001 and was opened
in August 2002. Once the garage was completed, work began
on the Family Law Center.
The impressive granite courthouse is designed to provide
a high level of security and still be conducive to the needs
of families during stressful legal proceedings. It incorporates
as much open space as possible in the entrance and public
areas and gives visitors a choice of using the elevator or
grand staircase.
Natural light is used wherever possible, and there are plenty
of private areas for delicate family court negotiations.
The courthouse was also designed to complement the 110-year-old
historic courthouse across the street. It was important to
Tarrant County to stay true to the exterior of the historic
buildings in downtown Fort Worth. The look was achieved by
the use of granite and brick as well as a green coating on
the window panes.
Before the facility was built, the family court operations
were spread throughout multiple buildings in downtown Fort
Worth.
Renovation/Restoration
Lamar County Courthouse
Submitted by: Harrison, Walker & Harper LP, Paris
Owner: Lamar County
Construction Manager: Harrison, Walker & Harper LP, Paris
Architect/Engineer: ArchiTexas, Dallas
Historical Consultant: Texas Historical Commission, Austin
In June 1999 the Texas Legislature established the Texas
Historic Courthouse Preservation Program to provide matching
grants to Texas counties for the restoration of their historic
courthouses.
In October 2000, Lamar County was awarded $464,500 to fund
the development of architectural plans and specifications
for the restoration of its 85-year-old courthouse in Paris.
In January 2002, the county was granted $3,535,500 for construction.
Designed in the classical revival style with Romanesque detailing,
the courthouse features the same Texas pink granite used on
the facade of the Texas Capitol in Austin.
The exterior of the courthouse remains almost entirely unchanged.
All original design elements, with the exception of the windows,
remain in place. The windows had been replaced in 1974 with
bronze anodized aluminum storefront windows, but as part of
the restoration they were returned to historically accurate,
butterfly casement sinker cypress wood windows. Sinker cypress
wood was utilized on all exterior fenestrations.
Aluminum storefront doors at the basement entrance were replaced
with wood and glass doors that match the originals. All of
the courthouse's historic pink granite was cleaned for the
first time since 1998, and period streetlights were added
to accent its historic appearance.
On the interior, all of the existing original historic fabric
and details were restored. Alterations that didn't conform
to the courthouse's 1916 appearance have been removed.
Most significantly, the drop-down ceiling in the district
courtroom that was installed to facilitate the HVAC system
has been removed, revealing the concealed balcony and outstanding
decorative plasterwork.
Floor plans were altered somewhat to provide much-needed
courtroom space and offices. This is most notable on the third
and fourth floors where jail cells no longer being utilized
were removed.
Sports/Entertainment
Mansfield Cinemark 12
Submitted by: Bob Moore Construction Inc., Arlington
Location: Mansfield
Key Players:
Owner: Cinemark USA, Plano
General Contractor: Bob Moore Construction Inc., Arlington
Developer: Kossman Development Co. Pittsburgh, Pa.
Architect: Beck Architecture, Dallas
The project was the first Cinemark to feature full-height
stone veneer. Coronado stone was the main exterior feature
and required close coordination between the concrete, sandblasting
and masonry subcontractors to achieve a final, safe product.
The stone veneer took more than two months to complete and
features numerous accent bands and color combinations.
Structural steel was a large component of the project. Steel
joists and beams are utilized at the roof and mezzanine levels,
and structural stub columns and decking are used at all auditoriums
to create the stadium seating.
To ensure that the steel was fabricated and delivered to
the jobsite in the proper sequence, 3D modeling via Tekla
Structures was incorporated. This product allowed the team
to determine potential issues before the steel was even fabricated.
The total floor area is 38,888 sq. ft., yet 81 tiltwall panels
had to be cast with an average area of 841 sq. ft. The complete
tiltwall panel area cast was about 68,100 sq. ft. or twice
the area of the slab.
The stadium seating component also meant that due to the
slab's numerous elevation changes, most of the panels were
cast outside of the building on casting beds and stacked as
many as three panels tall.
Further complicating the construction was the fact that a
residential area was only about 60 ft. west of the building,
limiting access during panel erection. Two "picking areas"
located inside an exit area and trash-compactor location solved
the access problem.
Transportation
Federal Inspection Services and APM Station
Submitted by: Clark/Mission, a Joint Venture, Houston
Location: Houston
Key Players:
Owner: Houston Airport System
Program Manager: The PB Team, Houston
General Contractor: Clark/Mission, a Joint Venture, Houston
Project Architect: PGAL Architects, Alexandria, Va.
Structural Engineer: Walter P. Moore Engineers + Consultants,
Houston
MEP Engineer: Burns DeLatte & McCoy Inc., Houston
Civil Engineer: PTI Inc., Houston
The Federal Inspection Services building is the major component
of the International Services Expansion Program for the Houston
Airport System at George Bush Intercontinental Airport.
The 850,000-sq.-ft. FIS facility, in conjunction with the
new Terminal E constructed for Continental Airlines, dramatically
expands the airport's international air traffic. The FIS building
centralizes U.S. Customs and Border Protection services for
international flight arrivals for Terminal D and Terminal
E and all ticketing security screening and customs inspections
of international passengers and baggage.
The FIS building superstructure consists of three main floors:
a basement, first and second floors as well as two mezzanine
levels. The basement floor houses the international baggage-handling
area accessed by two tug ramps on the east side that connect
to an existing airport operations service road.
The first floor contains the baggage-claim hall with 12 baggage-claim
devices containing more than 2,800 lin. ft. of presentation.
The floor also includes the baggage recheck hall and the meet-and-greet
lobby, which is set out by its architectural features of curved
ceilings, designed terrazzo flooring and artwork column covers.
The second floor houses customs' primary inspection hall
with 84 passport-inspection booths in a natural-light open
area. Also on this floor is the in-transit lounge, customs
offices and the over-roadway sterile and secure pedestrian
bridges that connect Terminals D and E and Continental's international
ticketing lobby.
The facility, which can process 4,500 international passengers
per hour and 190 pieces of luggage per minute, is the largest
single federal inspection services building in the country.
|