|
Lift-Slab Achieves Fine Tuning
Bartlett Cocke Hits High Notes at Trinity
University
by Jennifer Hiller

An aerial view shows the Trinity
Univesity campus in San Antonio, where the Ruth Taylor
Art & Music Center is undergoing an extreme makorver.
(Photo by Aero Photo courtesy of Bartlett Cocke.) |
A massive facelift by San Antonio-based Bartlett Cocke will
add much-needed ceiling height - not to mention a new music
and arts center - to Trinity University when it completes
this month.
The $16 million renovation and addition project at the campus
in San Antonio used the lift-slab method of construction to
raise ceiling heights and bring an additional 20,000 sq. ft.
of space to the Ruth Taylor Art & Music Center, which
will house the art, art history and music departments and
includes classrooms, studios and sound-proof faculty offices
and recital rooms.
Portions of four existing 1950s structures were gutted or
partially demolished to make way for a unified single building.
"It's a rebuilding and an extreme makeover of buildings
on the same footprint," said John Greene, director of
the physical plant at Trinity. "We added some square
footage. We vacated the existing building. A portion of it
was a one-story section we totally demolished. All of the
exterior walls and interior walls were demolished when we
raised the ceilings."
Although the lift-slab method hasn't been used widely since
the 1980s, the construction technique was common in the 1950s
and 1960s when most of the structures at Trinity were built.
"Many of the early buildings on the Trinity campus used
the lift-slab method of construction," Greene said. "It's
not common."
To avoid a complete demolition of the existing buildings
and to save money, San Antonio-based Kell Muñoz Architects
Inc. decided to stick with the original lift-slab method,
said project manager Geof Edwards. "We moved the floors
of the original building with a crane," he said. The
new concrete structures tie into existing lift-slab concrete
floors, which were relocated to make each of the floors level
throughout the building.
"It was originally a series of building built independently,"
Edwards said. "They needed more space. The buildings
were on different levels because of a slope, and handicapped
access was an issue."
Greene said the renovation raised ceiling heights in the
arts center from about 10 ft. to 15 ft. The original buildings
didn't have air conditioning. "We were trying to put
up a cheap building in the 1950s and 1960s," he said.
Roger Hoffmann, assistant project manager with Bartlett Cocke,
said the building broke ground in October 2004, although some
demolition work had been done prior to that. In addition to
the floor slabs, two of the original stair towers also were
preserved. "I've never seen a new project use lift-slab,"
he said.

An aerial vew shows the 117-acre
campus and the universitys Northrup Hall (left),
completed by Bartlett Cocke in 2004. (Photo by Aero Photo
courtesy of Bartlett Cocke.) |
Hoffman said the biggest difficulty on site wasn't the novelty
of the lift-slab work, but the tight spaces on campus. "There
was hardly a place to pull an 18-wheeler around to drop masonry,"
he added. "It had to be brought in on dump trucks instead.
We utilized the tower crane extensively because of the trees
we were trying to avoid and the limited space to maneuver
on campus."
Architects tried to keep the original 1950s look and feel
of the campus, even while renovating and adding new structures.
"We used the Trinity brick to continue the theme of
the campus," Edwards said. "But we did introduce
some aluminum composite panels near the courtyard."
The scale of the new three-story structure serves as a transition
between >> the original low-slung campus buildings and
the much larger, recently completed main administration building,
he said. In 2004, Bartlett-Cocke completed the $23 million
Northrup Hall, an administration and academic building that
is the centerpiece of the 117-acre campus.
The Taylor Center features a dramatic sky-lit three-story
lobby with balconies at the upper levels and vertical glass
slots at the north and south facades. A single-concrete column,
which supports a canopy over the main entrance, references
similar columns on the adjacent administration and student
services buildings. Deep sunshades protect the extensive glazing
on the south façade.
Edwards said the lobby knits together and organizes the three
wings of the building - the art and music wings and the pathway
to the concert hall.
On the north wing of the building, a series of saw-tooth
clerestory windows flood the third floor painting and drawing
studios with natural light. A glass wall separates the studios
from an east-facing balcony that is shaded by a series of
large existing oak trees.
The west wing houses the music department and includes isolated
floors and special wall construction to prevent noise from
traveling. "Students will be able to play in their professors'
offices without anyone else being disturbed," Hoffmann
said.
The new center also solves a space issue for Trinity. Students
and faculty in the art department previously used an outdoor
courtyard that was near the entrance to the performing arts
hall, causing pedestrian traffic issues. But now the arts
department has been moved and the first-floor art studios
open onto a work patio.
Edwards said an existing concert hall also was renovated
with an expanded back-of-house area that includes dressing
rooms, additional instrument storage and a freight elevator.
Stage expansion nearly doubled the size of the performance
area and new lighting and sound equipment brought the facility's
technologies up-to-date.
Jeni Cobb, project manager with Perkins & Will, said
the South Building will be ready for students and faculty
by the fall semester.
Architects worked to disguise the size of the buildings in
comparison with others on the campus so that the new complex
would not overwhelm the site. "We tried to complement
the adjacent buildings and keep the scale of this one down,"
Cobb said. "We wanted to keep with the campus vernacular."
The site slopes 18 to 20 ft. down to Harvey Lake. "It
was a big design issue as far as landscaping and saving the
trees," Cobb said. "It has a beautiful view to the
lake that we worked with."
But the slope and pond also presented one of the biggest
construction challenges at the site, hemming in construction
equipment and necessitating a large amount of dirt work, Massey
said. "When we started we had a 22-foot cut," he
said. "We had to contend with the pond. All of the water
around that site funnels to the lake. When we did the dirt
work we had monsoons."
The topography gave architects a way to hide the central
plant - by burying it on the slope. The single-story, 6,827-sq.-ft.
plant includes belled piers and a slab-on-grade. Roof framing
is structural steel and metal deck. Below-grade walls are
concrete, while the two buildings sides above grade are faced
with brick veneer and CMU backup. The plant will >>
provide chilled water for the complex and backup the campus
utilities system.
On the four-story South Building, the foundation system includes
straight-shaft drilled piers and a first-floor slab-on grade,
while the concrete building frame includes concrete columns
and pan slabs at levels two, three and four and the roof level.
At level one, three sides of the wall are cast-in-place concrete
as are the stairs.
The building veneer is a combination of face brick and cast
stone with CMU backup along with a curtain wall and storefront
systems.
|
Key Players
|
| Owner: |
Trinity University, San Antonio |
| Contractor:
|
Bartlett Cocke, San Antonio
|
| Architect: |
Kell Muñoz Architects Inc., San Antonio |
|