|
Expansion Made Efficient
A New Hospital Paradigm
Travels the Fast Track in Katy
By Rob Patterson
|

A rendering shows the centers redesign with two
towers one five stories and the other eight
connected by a central atrium. (Image courtesy of PageSoutherlandPage.)
|
The $66 million Memorial Hermann Katy Hospital creates a
new paradigm for hospital facilities and serves as a template
for the Houston-based health-care giant's expansion of services
within the greater Houston area.
The seven-story, 307,000-sq.-ft. structure is being built
as a co-venture by the Austin office of Hensel Phelps Construction
Co. and Houston-based SpawMaxwell Co. under a guaranteed-maximum-price
contract.
Ground was broken in April 2005 for the project, which replaces
an existing Memorial Hermann hospital in the Houston suburb
of Katy. Construction will be completed at the end of September
for a December opening.
The contractors on the 132-bed facility have faced a fast-track
schedule. "If you've built a hospital before, this is
not a hard job," said Paul Stirling, Hensel Phelps project
manager. "What makes this hospital hard is the speed.
"Imagine putting the shovel in the ground on April 1
of '05, and by Sept. 30 of '06, your punch list is going to
be 80 to 90 percent done. For the next two months you assist
the owner while equipment and furniture are moved in and testing
is performed to ensure everything is working properly to begin
treating patients on Dec. 1."
Dax Studebaker, project superintendent for Hensel Phelps,
said the first difficulty was value engineering about 10 percent
out of the project to get within the owner's budget. "We
worked closely with the design team and the owner to come
up with a list of ideas to save money while the owner would
still get the desired end product," he added.
The team was able to reduce the cost by $6 million and value
engineer most of it within two weeks. Among the reductions
were shaving the contractor's allowances, reducing mechanical
costs by about $1 million and shelling some areas of the building
intended for future use.
Meeting the rapid timetable was aided by paving a substantial
portion of the 65-acre site adjacent to Interstate 10 prior
to laying the building's foundation. "A lot of the site
paving in front was done when we started the foundation, and
it was beneficial because we had a lot of working surfaces
to work from for material storage and site access," Stirling
said.
A final total of 470,000 sq. ft. of parking was poured using
9,300 cu. yds. of concrete. The campus will include a five-story,
129,000-sq.-ft. professional office building being simultaneously
constructed by D.E. Harvey Builders of Houston.
The hospital structure is primarily reinforced, cast-in-place
concrete. The frame of a two-story administrative wing is
structural steel, and steel is being used in the lantern structure
atop the central tower, an identifying icon being used on
all Memorial Hermann facilities. Concrete tilt-wall was used
on the mechanical wing at the rear of the building.
The exterior is a combination of ribbon windows on the tower,
window wall on the lower levels, precast concrete panels,
calcium-silicate masonry units and some plaster on the lower
levels. The lantern includes aluminum panels.
The 6-ft.-thick concrete foundation slab is supported by
137 bell piers drilled 15 ft. into the dirt. A total of 18,521
cu. yds. of concrete was poured for the structure.
The building's design was developed as a prototype for the
Katy facility and a hospital under way in Sugar Land that
is smaller in size by approximately 60,000 sq. ft.
"We've been one of Houston's most prolific developers
in any industry, and certainly the most prolific in the health-care
industry," said Marshall Heins, vice president of construction,
real estate and support services for Memorial Hermann Healthcare
System. "As we've done this, we've determined that we
would like to move to more of a standardized type of development
construction.
"When we went out to bid for architectural services
and engineering and all the other consultants, we said, 'Look,
we're going to basically do this same building twice, and
then probably do it more in some new markets in the Houston
area, so bid your fees accordingly."
Building two similar hospitals and adjacent professional
office buildings simultaneously helped cut material costs,
too. "We were able to aggregate our spending on medical
equipment, glass, steel, concrete," Heins said. "By
placing much larger orders, we can basically negotiate the
price of those at the time."
The building design breaks away from the traditional institutional
style of hospitals, taking cues from the hospitality industry
and contemporary office buildings. "We were basically
looking at three things that we felt identified as best practice
in health care: operational efficiency, consumer appeal and
family-centered care," said Mark Vaughan, senior medical
planner for WHR Architects in Houston.
"One of our beliefs is that people don't want to be
housed as patients in an institutional environment. If we
can make them feel more at home or in more of a hospitality
environment, they can heal much faster and feel happier. The
days of the concrete floor and CMU or tile walls, the pale
greens and Pepto-Bismol pinks are gone."
The central patient tower, with only private rooms, is configured
around a 30-bed nursing-unit. On the ground level is a two-story
public concourse.
The tower features an on-stage/off-stage division between
the patient-care spaces at the front of the tower and support
facilities at the back, with separate elevator banks. "The
idea is that ancillary support and equipment and dietary,
linen and supply carts that go up and down the building are
arriving on an offstage area, making them less intrusive for
patients and visitors," Vaughan said.
The design required extra coordination for the builders.
"It's got a lot of tiers and levels and it's not a box,
per se," Studebaker said. "Each footprint steps
in and gets smaller as it goes up until you get to level four."
From level four up, the footprint is consistent.
"It's got a lot of radiuses and non-right-angle type
construction."
The tight timeline meant proceeding without following normal
scheduling routines. "We were working fast and furious
to keep up with the desired move-in date," Vaughan said.
"We were issuing multiple packages for site, foundation,
building-shell and core and interior build-out. We were under
the gun to keep all that rolling. At the same time we were
adjusting things to meet the ultimate budget of the project."
The builders had to be flexible as the structure went up.
"We made some suggestions on the bid packages, and they
couldn't necessarily produce the drawings fast enough for
us," Stirling said. "So there were literally subcontractors
bought on the basis that they would be starting late."
Stirling said the project is truly a 50-50 co-venture between
Hensel Phelps and SpawMaxwell, even though the former is primarily
known for its expertise in shell construction and the latter
specializes in hospital interior build-outs. It also required
the contractors to be versatile in the tasks they performed.
"We've built two bridges to access the feeder road of
IH-10," Stirling said. "And it appears that we are
going to do some feeder-road work that TxDOT is going to require
of Memorial Hermann."
He said that Hensel Phelps has not done road work for a number
of years. "We're getting a widespread gamut of all the
work out here," he added. "But that's what being
full-service is all about."
|
Key Players
|
| Owner: |
Hermann Healthcare System,
Houston |
| General Contractors:
|
SpawMaxwell Hensel Phelps,
a joint venture between SpawMaxwell Construction LP (Houston)
and Hensel Phelps Construction Co. (Greeley, Colo., Austin)
|
| Architect: |
WHR Architects Inc.,
Houston |
| Structural Engineer:
|
Haynes Whaley Associates
Inc., Houston |
|