Fairy
Tales Come True at DFW
With the With the Completion of SkyLink, the future looks bright at DFW.
By Lesley Hensell
Since construction first began in September 2002 on the Dallas/Fort
Worth International Airport's new Automated People Mover,
the airport has been experiencing nightly re-enactments of
Jack and the Beanstalk.
Like Jack, who awoke with the morning sun, pilots, workers
and passengers at DFW arrived early in the day to discover
an enormous "beanstalk" growing at the airport.
Actually, what they saw growing are gigantic concrete pillars
that are part of the airport's new $872.9 million APM, and
because the nearly 5-mi.-long guideway for the APM had to
be constructed on the airfield side of the terminals, most
construction activity took place at night.
That chapter of the fairy tale is almost over as the APM is
expected to begin speeding passengers between the airport's
five terminals on time and on budget in early 2005 at $26,440
per lin. ft.
|
The airport's size has long created difficulty for passengers
attempting to make connecting flights, and about 65 percent
of the airport's passengers are connecting passengers. Dubbed
SkyLink, the APM system will link the airport's existing terminals
A, B, C and E, as well as the new International Terminal D
and a proposed Terminal F.
A bridge to billions
The APM project is part of a $2.6 billion Capital Development
Program undertaken to update the airport's infrastructure
over five years. Airport officials project that this investment
will generate an additional $34 billion in economic impact
on the North Texas economy and 77,000 new jobs over the next
15 years.
In addition to the APM, the Capital Development Program includes:
Enhancing the airfield with extensions of existing runways
as well as enhancements to the service road system
Development of International Terminal D, a 2-million-sq.-ft.
terminal that will include 28 gates, a three-level roadway
system, an 8,100-space parking garage and an integrated 298-room
Grand Hyatt Hotel
Support infrastructure projects, including upgrades
to the airport's fueling system and signage
Roadway and parking infrastructure projects, including improvements
to access roads and expansion of several parking facilities
Connections are key
The airport's goal is to connect each passenger to his
or her next flight in 30 minutes or less, which meant the
current people-mover system had to be replaced.
"It's virtually impossible to connect passengers through
the existing system or across the road by busing,"
said Clay Paslay, executive vice president for airport development
at DFW. "What drove us to the final decision was the
growth of American [Airlines] into multiple terminals."
With the construction of Terminal D, American Airlines will
be in four terminals, making it even more difficult for
passengers to meet their connecting flights without a better
system in place. In addition, DFW is one of only two airports
in the country serving as a hub for more than one carrier.
Obviously, the replacement system had to be constructed
with minimal impact to airport operations. The airport considered
several options, from underground trains to a system that
would run on the roadside or roofs of the terminals, Paslay
said.
Going underground would be astronomically expensive, and
a roadside system would have required the fronts of terminals
to be blocked during construction, Paslay said.
In the end, a fully automated, elevated APM that runs on
the airfield side of the terminal was chosen.
Setting the stage
The airport determined that the best way to get the APM
constructed, without disrupting flights, was to construct
it at the roofline on the airfield side. But that strategy
required a huge commitment from the airlines, said Andy
Bell, SkyLink managing executive.
"American Airlines even set aside two people whose
full-time job is to coordinate with our daytime and nighttime
operations," said Perfecto Solis, DFW Airport's assistant
vice president for program development. "On the flip
side, we gained a thorough appreciation of airline operations.
It was a great education both ways."
Because of the immense size of the 12,000-plus construction
crew, as well as the proximity of the project to workers
unfamiliar with the construction process, the airport went
out of its way to put extra safety measures in place.
"To the flight crews, what we are doing looks intimidating,"
Bell said. "So we didn't just go by OSHA standards,
but went further with higher fences and extra safety people."
The airport also established a 40-hour, bilingual safety
training program for the Capital Development Program's construction
personnel. As a result, the incident rate for the program
is one of the lowest in the nation at .46 percent, compared
to the national average of 4.1 percent, Paslay said.
To make room for the APM and give construction crews a right-of-way,
most jet bridges had to be extended further from the terminal.
More than 4,000 ft. were added to existing bridges at 68
of the airport's 113 gates, and several fueling stations
were moved.
The construction team also had to drill and build on the
airfield's 30-year-old foundation, which covers a web of
fuel, electrical and water lines. "We invested in leading-edge
equipment for testing," Bell said. "And we had
no major hits. We missed all fuel lines and had no electrical
disruptions. As long as we remain invisible, everyone is
happy."
Taking the red-eye approach
When work began on the airfield side of the terminal, most
construction had to take place at night to avoid disrupting
airline operations. Specific gates were scheduled to close
each night at about 9 p.m.
The airlines had to move planes, baggage-handling equipment
and other items away from the construction area. Then, construction
crews moved in, completed a task and had to be clear of
the area by 6 a.m.
"Nighttime closures impacted about 70 percent of all
gates," Bell said. "As of today, we've had 30,000
individual gate closures."
At the peak of construction, up to 25 gates could be closed
on any given night, Solis said. "At 9 o'clock at night,
it looked like an airport. But by 10:30, it looked like
a ship- building yard," he added.
At around 4 a.m. or 5 a.m., work would stop and crews would
begin cleaning up. In most cases, every trace of ongoing
construction had to be removed from the area by 6 a.m.
"Every night, there was a virtual army of contractors
and materials just waiting for the predetermined hour too
start work," Paslay said. "When work could begin,
it was like ants pouring out of an ant hill. Then, like
Cinderella, the clock would strike and they had to get out
of there."
Column construction goes mobile
The new guideway looks similar to a highway overpass that
goes in a continuous circle around the airport. It is held
up by 370 columns, which range in height from 50 to 70 ft.
The typical column shape is oval and averages eight ft.
by six ft. in depth.
Usually, such structures would be cast in place. But for
those columns, which rise above the airfield, casting in
place would have required long gate closures, which was
not an option. The columns on the airfield had to be pre-cast
in another location and then erected onsite. While 118 columns
were cast in place, 252 had to be pre-cast. Of those, 1,008
segments were fabricated offsite. Approximately 2,000 tons
of reinforcing steel and 13,000 cu. yds. of concrete were
used in the pre-cast segments.
Each column sits on an 8-ft.-drilled shaft that ranges in
depth from 30 to 80 ft. undergound. The four column segments
and a pre-cast bent were held together by tension rods during
erection. After all the components were erected, post tension
cables were looped through the whole column assembly and
the base support and stressed.
The columns are connected by the guideway on which the APM
will travel. The guideway features a built-in heating system
with warm-water-and-glycol filled tubing to keep the track
clear of frozen precipitation. When the temperature reaches
37 degrees and the air hits 60 percent humidity, the solution
flows through the system to prevent the accumulation of
snow or ice.
Going up
The guideway connects the airport's existing and future
terminals, which will include two SkyLink stations each
that will run approximately 480 ft. long. The stations come
equipped with synchronized doors, passenger information
systems, escalators, stairs and elevators. The stations,
which are currently built and awaiting some finish-out,
will eventually have trains pull in on both sides.
When the design concepts for the stations were originally
presented, engineers determined that 48 columns would be
needed to support each structure. But this disrupted the
minimalist, clean design that project designers wanted.
Instead, 10 large "hero" columns were erected
in each station. These 8 ft. by 10 ft. columns were pre-cast
in two segments. They were hollow in the middle to reduce
weight and facilitate both transportation from the pre-cast
yard and placement by crane. Once set in place, numerous
post-tensioning tendons were routed through the two column
segments and the supporting base. Those columns were organized
in pairs and a large, steel, double-plate bent was placed
on each column pair. The result is main station bents that
support the bulk of the building loads and all of the train
and guideway loads.
The stations' interiors are set off by minimalist spotlights.
During daytime hours, most lighting is provided by natural
sunlight streaming through a bank of towering windows on
either side, from which passengers will have commanding
views of the airport and downtown Dallas. Each station also
will sport terrazzo tile flooring.
The guideway also leads to a 100,000-sq.-ft. maintenance
and control facility.
All aboard
Once the stations and guideway are complete, the project
will be turned over to Bombardier, the vendor chosen to
provide the APM train system. The system should be ready
for public use in the first quarter of 2005, with testing
scheduled to begin as early as this month.
The airport has purchased an initial fleet of 64 silicon-coated
fiberglass cars, each about the size of a city bus, which
are suspended on rubber tires. They will travel in pairs
at speeds of up to 35 mph.
Twenty-four two-car trains will be fully operational at
the outset and will be able to transport 5,000 passengers
per hour, per direction, for a total of 10,000 passengers
per hour. Ultimately, more cars can be added to transport
a total of 8,500 passengers per hour, per direction, for
a total of 17,000 passengers per hour.
Talking it over
The size and scope of the project required Paslay and his
team to perform detailed planning years before construction
began. Before launching any phase of the Capital Development
Program, the airport constructed an onsite facility where
all decision-makers could log on to the same computer network.
"Collaboration is vital," Bell said.
"We are dealing with a huge mixture of multiple companies
and egos." And when challenges arose, they had to be
resolved quickly.
"We resolve conflicts as we go," Solis said. "We
get everyone in a room and say that nobody is leaving until
this is resolved."
| PROJECT
TEAM: |
| GENERAL
CONTRACTOR/CONSTRUCTION MANAGER: |
Hensel Phelps Construction
Co. |
| OWNER: |
Dallas/Fort
Worth International Airport Board |
| ENGINEERING
FIRM OF RECORD: |
Kellogg Brown and
Root |
| ARCHITECTS
OF RECORD: |
Corgan and Associates
|
| DESIGN
ARCHITECT: |
David Mason of Corgan |
| STRUCTURAL/CIVIL
ENGINEER: |
Kellogg Brown and
Root, Fresse & Nichols, Civil Structures |
| STRUCTURAL
STEEL CONTRACTORS: |
North Texas Steel,
Bob McCaslin Co. |
| MECHANICAL
ENGINEER: |
Fresse & Nichols,
Evans & Evans, Lopez Garcia Group |
| ELECTRICAL
ENGINEER: |
CP&Y, Lopez Garcia
Group, Evans & Evans, Fresse & Nichols |
| PLUMBING
ENGINEER: |
Evans & Evans |
| STRUCTURAL
STEEL: |
Kellogg Brown and
Root, Fresse & Nichols, Civil Structures |
| PRECAST
CONCRETE: |
Kellogg Brown and
Root, Fresse & Nichols, Civil Structures |
| PRECAST
CONCRETE CONTRACTORS: |
Martin K Eby Construction,
Bexar Concrete Works |
| CONCRETE
CONTRACTORS: |
Dalcan, Omega, Addison
Harrington, McCarthy, Gilbert of Texas |
| MASONRY: |
Lucia, Innovative
Masonry, Clayton Masonry |
|