|
Sea Change
Corpus Christi Airport Renovation
Reflects Gulf Coast Heritage
By Jennifer Hiller
A redeveloped Corpus Christi International
Airport recently reopened with a $34 million facelift that
takes cues from the region's surf, seagulls and Hispanic heritage.
The project included the overhaul of the Hayden W. Head Terminal,
taking a 1958 concrete building with long and winding pathways
and creating a 165,000-sq.-ft., glass-fronted city landmark
in its place.
DMJM+Harris of Houston was the construction manager and
the general contractor was the Corpus Christi-based Fulton/Coastcon.
The Houston office of Walter P. Moore was the structural engineer.
The project broke ground in March 2000, but construction
went through seven phases to accommodate the operating airport
and full flight schedule. The final steps included the relocation
of the news and gift shops, additional food and retail areas
and the relocation of the security checkpoint.
Gensler Architects of Houston designed the two-story terminal.
Architect Richard Maxwell said the firm met for more than
a year with the Corpus Christi City Council, the airport board
and local residents in public hearings to get input.
"We took the ideas of seagulls and wings and the surf
and water," Maxwell said. "We wanted to make sure
that those concepts came across to the public with the waves
in the front of the terminal."
The waveform of the roof is the airport's most distinctive
design element, but an abundance of tile, arches and stuccos
walls also recall the area's Hispanic heritage. The city implemented
a conceptual landscape plan that features tropical plantings.
The wave-shaped canopy was partially
constructed from the existing canopy roof framing to save
money and help the environment through recycling. Several
existing canopy foundations also were reused to support the
new canopy.
Structural engineers said they looked at several options
for the building, including steel-framed versus concrete-framed
construction, reusing portions of the existing steel-canopy
roof versus using all new steel for the new canopy and using
precast cladding versus concrete masonry units.
Based on the costs and the construction schedule, Walter
P. Moore engineers decided to go with a cast-in-place concrete
frame consisting of a new ground-level slab on carton form,
wide-pan joist construction for the second floor and steel
framing for the roofs and canopy.
The long-span, reverse curvature roof beams with the compound
curvature eyebrow contributed to the project's unique maritime
look. To accommodate rolling and transportation, a splice
was provided at the inflection point of the double curvature.
Because most of the existing terminal had to be torn down,
a temporary connector had to be built between the ticket lobby
and the west concourse before major construction could begin.
Baggage claim and rental car companies had to be relocated
to the west of the terminal.
Reusing the center concourse restrooms, a portion of the
concession and the east and west concourses and their gates
reduced temporary facilities costs and the impacts to airport
travelers and employees.
. "Basically we built a new airport in the footprint
of the old airport," said Jimmy Bednorz with Fulton/Coastcon.
"The original building had some structural problems.
We probably tore down 95 percent of it."
The Sept. 11 terrorist attacks slowed construction, stopping
work altogether for several days and giving workers new restrictions.
"For about six weeks we couldn't park near the construction
site," Bednorz said. "We had to shuttle workers
in from a remote parking lot."
Sept. 11 also caused some design changes. Parking lots had
to be reconfigured and the security checkpoints had to be
moved. Architects had to give additional square footage to
the security areas to accommodate the additional equipment
and higher number of screeners required.
"We were fortunate in that many of our plans were still
on the drawing board," said airport marketing coordinator
Amy Gazin. "The changes for us were really on paper."
The airport renovation and addition were part of a city
plan to stop Corpus Christi residents from driving to San
Antonio, Houston or Austin to find lower fares. According
to the Texas Department of Transportation, the city loses
225,000 passengers a year to San Antonio.
Gazin said one of the biggest changes for passengers is a
shorter walk from the ticket counter to the gates. The longest
walk to get to a gate in the new terminal is about 540 ft.,
compared with 820 ft. previously - saving passengers nearly
an entire football field of walking.
Also, a roadway renovation added about 580 long- and short-term
parking spots, nearly doubling the amount of available parking.
Parking spots also were moved closer to the terminal, and
drivers dropping off or picking up passengers are greeted
by a covered terminal drive.
The project was funded by FAA grants, city bond money and
airport passenger charges.
Contractor box:
Owner: City of Corpus Christi
Client: Department of Aviation,
City of Corpus Christi
General Contractor: Fulton/Coastcon,
Corpus Christi
Construction Manager: DMJM+Harris,
Houston
Structural Engineer: Walter
P. Moore, Houston
Architect: Gensler, Houston
Associate Architect: Bennett,
Martin, Solka and Torno, Inc., Corpus Christi
Civil Engineer: Urban Engineers,
Inc., Pennsauken, N.J.
MEP Engineer: ccrd partners,
Houston
Civil Landside Engineer: Urban
Engineering, Annadale, Va.
|