|
Surf and Turf
Luhr Bros. and King Fisher Reopening
Corpus Christi's Packery Channel
By Jennifer Hiller
Packery Channel broke ground during the summer on North Padre
Island, but the $30 million plan to dredge a new boat channel
from the Gulf Intracoastal Waterway to the Gulf of Mexico
has been more than 80 years in the making.
About 50 percent complete and expected to open in August,
the U.S. Army Corps of Engineers project will reopen a channel
that silted shut in 1923.
Dredging attempts at Packery Channel in 1890, 1938 and 1954
eventually failed, and six hurricanes have reopened the channel,
but none permanently. The channel takes its name from the
"packeries" that used the pass in the mid-1800s.
Businesses operating along the channel sold bird feathers,
cattle and turtles.
The general contractor is a joint venture between the Illinois-based
Luhr Bros. Inc., which owns a rock quarry and has done other
marine and jetty projects, and the Port Lavaca-based King
Fisher Marine Service, which specializes in dredging. Both
companies have worked with the Corps of Engineers on other
projects.
For years, Corpus Christi leaders talked of reopening the
channel because it would provide the most direct access for
resident boaters to reach the Gulf. The project is also seen
as a lynchpin for resort development on North Padre Island.
The project had some environmentalists concerned about storm-flooding
implications, but the Corps of Engineers says it will benefit
the Upper Laguna Madre by increasing circulation and water
quality.
Rocking Out
The project will use mechanical water-based dredging, hydraulic
dredging and mechanical land-based dredging to create the
8-ft. channel. The two rock jetties will extend 1,400 ft.
into the Gulf and about 900 ft. onto the land, and the crown
width of 10.5 ft. will be covered with a concrete walkway.
Andrew Smith, civil engineer with the Corps of Engineers,
said storm wave heights, prevailing winds and the placement
and cost of stone were considered when designing the jetties.
The jetties are oriented at 12 degrees north of the shore
to provide shelter from the prevailing southeast winds in
the summer and prevent wave action inside the channel.
The jetty's limestone base and core-42,500 tons of blanket
stone and 27,800 tons of core stone-will be topped by 57,500
tons of granite. "Granite is the densest readily available
rock," Smith said. "You get a lot more weight and
better protection from waves." More than 9,500 tons of
small limestone will be used as filler.
Luhr Bros. will build the first 500 ft. of jetty from the
beach, then go to a barge-based operation, Smith added. All
of the landside work will be complete before the channel is
opened.
The project also features a sand-bypass casing-the first
of its kind on the Texas coast. Workers used directional boring
to place 30-in. high-density polyethylene below the channel.
"It's a new idea," Smith said. "There should
be no net transport of sand on this part of the beach. But
if the city starts to add sand on one side of the channel
and the other side is starved, sand can be mined from one
side to the other. You can rebuild the beach on either side."
More than 106,000 cu. yds. of sand have been dredged from
a 2-mi. section between the Intracoastal Waterway and an existing
bridge at State Highway 361. To prevent erosion and protect
the existing floodwall, the dredged sand has been used to
raise the grade along the channel from 2 ft. to an average
of 6.5 ft.
Most of the dredge material from the channel construction-about
730,000 cu. yds.-will be placed to the south of the channel
in front of an existing seawall via hydraulic dredge. That
placement will increase elevation to 3 ft. with a minimum
beach width of 350 ft. The beach restoration is one of the
key environmental aspects of the project, Smith said.
Because scour is a potential problem in the channel, protection
is provided along either side of the highway bridge and through
the bridge section. Woven geotextile filter cloth, limestone
and tremie-placed concrete will be used directly around the
bridge piles.
"That is the choke point," Smith said. "It's
the most narrow point of the channel, and the only place for
the tide to go through."
Throughout construction, the contractors have been careful
to watch for sea turtles that nest from March through September,
prevent the destruction of sea grasses and avoid disturbing
the piping plover, a threatened bird that spends its winter
along the Texas Gulf Coast.
"We do regular bird surveys to see if they're moving
around or being affected by the work," Smith said. During
turtle-nesting season, workers do a daily survey for turtles
and eggs, and vehicles larger than a pickup truck are escorted
by a four-wheel drive that acts as a lookout.
Wayne Boyd, president of King Fisher Marine Service, said
the construction at Packery Channel has required few subcontractors
because it calls for primarily rock and dredge work. Erosion
Prevention of Houston is supplying concrete matting for the
channel. Workers began laying the matting in mid-September.
The Dune Doctors of Pensacola, Fla., will handle native-grass
planting.
Shoring Up Funding
The Water Resources Development Act of 1999 authorized the
work, although piecemeal federal funding for $19.5 million
of the project has been an ongoing issue.
The first construction funds were released in 2002, and by
the end of 2003 Congress had sent $5.5 million for the project.
Another $4.7 million was released for 2004, including $400,000
in last-minute funding that was released in late spring so
work could continue through early fall.
Because Packery Channel has never appeared in the president's
budget, project supporters and area politicians have been
anxiously watching the 2005 House and Senate budgets as they
move through Congress. Texas Sen. Kay Bailey Hutchison has
been a key supporter of the project, shepherding funding through
and calling Packery Channel one of her top priorities for
the state.
The project needs another $9.3 million in congressional funding
for fiscal year 2005 to wrap up by the estimated completion
date.
"That's what it would take to finish the project on
time," said Marilyn Uhrich, public affairs specialist
at the U.S. Army Engineer District in Galveston.
By early fall, only $3 million had appeared in the House
version of the budget. Supporters were hopeful that all funds
would be in place by the time both houses of Congress agree
on a budget.
Another $10.5 million in local funding comes through a city
of Corpus Christi bond election and a $1 million grant from
the Texas General Land Office.
Also, the Texas Parks and Wildlife Department in May awarded
the city of Corpus Christi a $500,000 grant to build a two-lane
boat ramp, parking lot, road and three docks. The city is
matching that grant with $205,621. The ramp will be built
on the north side of Packery Channel.
Upon completion, Packery Channel will be turned over to the
city of Corpus Christi, which will be responsible for maintenance
dredging and future beach remediation.
"This is only an estimate, but the first dredge after
the opening will be somewhere in the three- to five-year range,"
said Tom Utter, assistant city manager in Corpus Christi.
"Then we'll have to dredge every three years or so."
Key Players
Owner: U.S. Army Corps
of Engineers
General Contractor: Luhr
Bros. Inc. and King Fisher Marine Service Joint Venture
Native grass planting: Dune
Doctors, Pensacola, Fla.
Concrete matting: Erosion
Prevention, Houston
|