|
The Power of Teamwork
Energetic Schedule Brings Project
Online in San Antonio
By Rob Patterson
To meet its summer peak power demands, San Antonio's City
Public Service needed a 200-megawatt power plant that could
come online at full load within 20 minutes. And the municipally
owned electric utility not only needed quick power, it also
needed the plant built quickly to meet possible summer 2004
demands.
Leon Creek Power Partners - a joint venture between the Steamboat
Springs, Colo.-based TIC-The Industrial Company and Utility
Engineering Corp. of Denver - was awarded the $43 million
Leon Creek Power Plant and went from a July 2003 groundbreaking
to generating power a mere 11 months later.
The two companies - who had partnered on other projects-
formed the joint venture after the city issued a request for
proposals to construct the plant. Utility Engineering provided
design and engineering services; TIC acted as the general
contractor.
Leon Creek Power Partners won the job thanks to a number
of factors in its proposal: "Price, experience, safety
record, the ability to meet the schedule and stability and
financial backing," said Frank Sanfi of Parsons Brinckerhoff,
who served as the owner's engineer and manager of the project.
City Public Service hired the firm to prepare the request
for proposal, evaluate the proposals and perform contract
compliance and on-site monitoring.
"It was an extremely aggressive schedule," said
Richard Cleveland, project engineer for TIC's Gulf Coast Region
division, based in Houston. "Initially there were a lot
of folks who felt that the schedule was unlikely to be achieved."
Two factors helped the project get up to speed. CPS had already
purchased four General Electric LM6000 gas-fired, simple-cycle
turbines, each capable of generating 50,000 megawatts. The
turbines are able to begin generating power within 7 minutes
and hit full capacity in less than 20 minutes, making them
ideal for peak production usage. And a site was readily available
adjacent to one of CPS's older plants, near Leon Creek at
the southern edge of the city.
"We had infrastructure here already," said David
Herbst, project manager for CPS. "We had a high-pressure
gas supply fairly close." A new 2-mi. pipeline was laid
to tap into the nearby main pipeline. "We also had a
switchyard that lent itself fairly well to adding on a dead-end
structure. We saved about $2 million with that. There was
water supply on site. And the land was free - we already owned
it." The older plant did create the complication of working
around preexisting underground pipelines and water supply.
To prepare the site, two cooling towers
from decommissioned turbines in the older plant were demolished.
A 5-ft. deep excavation removed some 40,000 cu. yds. of earth,
which was replaced with fill. "One of the concerns is
that the soil on site is a clay that swells up when it gets
wet," said Sanfi. The fill mitigated any potential vertical
rise underneath the plant.
Next, a 48,000-sq.-ft. reinforced concrete slab was poured
using 8900 cu. yds. of concrete. At 5 ft. thick, the slab
was not only designed to bear the load of the turbines and
ancillary equipment, but also to address the vibrations created
by the spinning turbines.
The four turbines were then installed, along with a fairly
sophisticated support system to maximize efficiency and address
environmental concerns. Each of the turbines is linked to
a selective catalytic converter to reduce emissions. "You
typically do not see those on a single cycle unit," said
Clinton Smith, project manager for Utility Engineering's Amarillo-based
Texas division. "It was a proactive move by CPS, who
are emissions-conscious. From the standpoint of the entire
community, they did a good thing there."
Since water supply is a concern in Central Texas, and the
plant taps into the heavily utilized Edwards Aquifer, a reverse
osmosis water-treatment system was incorporated into the plant
to create maximum efficiency.
The four turbines are controlled by on-site Dell Computer
servers using a Windows-based operating program and housed
in a prefabricated steel structure. The system is designed
to be controlled remotely by CPS's central dispatch facility,
allowing the plant to be brought online without personnel
on site.
In the end, teamwork overcame the demands of the tight construction
schedule, "This is one of the smoothest projects I've
been associated with," Cleveland said. "A lot of
that is due to CPS's support. We approached everything together.
The one thing we really enjoyed on this project is the true
team among TIC, UE and CPS."
|