|
How's Bayou?
Corps of Engineers Progressing
on Houston Flood Control Project
By Eileen Schwartz
Skeptics might say that the long-awaited Sims Bayou Flood
Control Project-approved in 1986 and started in 1994-is proceeding
at a snail's pace.
But look at it this way: The much-needed, $350 million project
in the shadow of Houston's towering downtown skyline is about
50 percent complete, and already it is providing welcome flood
protection for some residents, opening new hike and bike trails
and creating green habitats.
Ten miles of the once-narrow, serpentine bayou-from the mouth
of Sims Bayou to Cullen Boulevard-have now been enlarged and
otherwise enhanced to provide greater flood abatement. The
ultimate goal of the project, scheduled for completion in
2009, is to improve 19.3 mi. of the bayou from its mouth at
the Houston Ship Channel to Croquet Street and replace or
modify 20 bridges along the way.
Once this is accomplished, "approximately 3,500 existing
homes and 2,000 existing commercial structures will no longer
be in the 1 percent (100-year) flood plain," Alisa Max,
project engineer for the Harris County Flood Control District,
said in a recent progress report.
Max said the channel improvements are going forth in a manner
that protects and enhances the environment. For example, she
said that articulated concrete blocks that allow grass and
other vegetation to flourish are used in lieu of traditional
concrete.
"Instead of a trapezoidal channel, the new sections
of Sims Bayou have shelves creating plateaus, varying water
widths and varying side slopes, creating a more naturalistic
feel," she added. Max predicted that this once-neglected
south Houston area will soon emerge as an "environmentally
sensitive, aesthetically pleasing and publicly acceptable"
neighborhood.
The plan has already proved its worth, said Lizette Richardson,
Sims Bayou project manager in the Galveston office of the
Army Corps of Engineers, which is managing the project. Richardson
said that when Tropical Storm Allison hit the area in 2001,
the half-finished project helped detain the waters in the
Sims Bayou watershed "and avoided approximately $200
million in damages."
The local media have largely ignored
recent developments along the bayou. Michael deMasi, project
engineer with the Galveston district of the Army Corps of
Engineers, said the reason is the belief that "no news
is good news."
"Every once in a while there will be a little blip
in the newspaper about Sims, about more money or something
like that," deMasi said. "But other than that, everything's
going so smoothly, it's not a big news story unless somebody's
getting flooded."
At a section of the bayou just downstream from State Highway
288, where construction was recently centered, deMasi pointed
to some nearby hike and bike trails already finished and being
used. "They are not tied into anything right now, except
for a couple of streets," he added. "Eventually
they will go from downstream to Interstate 45 for about 19
mi. and tie in to all of the parks along the trail."
He pointed out the aesthetic touches that have been an integral
part of the project. "We're putting in a lot of trees
to make the area more environmentally sensitive," he
said. "Another feature is a deep fish pond. In the summer
when the water gets low, it gets real hot and this is bad
for the fish, turtles, snakes and alligators. So we put in
these deep areas where the animals can find cool water."
DeMasi said the improvement is taking a long time because
of its "sheer size," which involves, for starters,
2 million cu. yds. of excavation, 1.6 million sq. ft. of interlocking
articulated concrete blocks, extensive new wetlands and recreational
facilities, all the bridge replacements and the relocation
of two railroads.
He said funding problems have also slowed progress. "It
is a known fact that projects for the Corps of Engineers or
for any government agency take a long time," he added.
"It takes year after year for Congress to appropriate
funds. You then have to work with the locals and environmental
agencies. All those pieces have to come together before a
project even gets awarded."
A data sheet circulated last year by the Galveston office
of the corps underscored existing funding problems. It credits
U.S. Rep. Sheila Jackson-Lee, who represents the district
in which Sims Bayou lies, with pushing hard for optimal funding.
"However," it adds, "the current federal budget
ceilings lengthen the construction period resulting in an
estimated project completion of September 2009."
The Sims Bayou flood control project was originally authorized
in 1986 under federal flood control legislation. But environmentalists
and others opposed the original plans, which called for simply
deepening the channel and lining it with concrete.
Opponents wanted less concrete and more landscaping. Led
by the Sims Bayou coalition, a local environmental group,
a plan was developed with wider and deeper channels that would
detain stormwater rather than shunt it into the Houston Ship
Channel. The plan also devised ways for protecting and enriching
the area's natural beauty.
New design plans were drawn and a new cooperation agreement
was signed in 1990 by the Corps of Engineers and the Harris
County Flood Control District, the nonfederal sponsor. This
agreement was modified in 1992 and construction finally started
in 1994 with an initial completion date of 2006.
The original estimated cost of $244 million has grown to
nearly $350 million, and it probably will ratchet up again.
Eleven major contractors and numerous subcontractors have
been involved in the Sims Bayou project, with Lecon Inc. of
Houston getting the lion's share of the awards.
Top players also include E.R.H. Garver and Midwest Construction
of Nebraska.
DeMasi said Lecon has an advantage because of its Houston
base. "The out-of-state contractors may not know the
Houston connections," he added. "They have to do
a lot of work on their own getting permits and going through
the city of Houston to get things done."
The disputes that marked the beginning of flood control on
the Sims Bayou are apparently all water under the bridge now.
DeMasi and others said city, state, county and federal officials
are working in harmony with concerned private citizens.
"We've worked a lot with the Sims Bayou environmental
organizations and done a lot of things they wanted us to do,
like planting wildflowers in some of the reaches at the right
times of the year," deMasi said. He added that the environmentalists
helped the corps decide what native trees to use and where
to plant them.
"All that had to be in conjunction with the intent of
the project, which was to get the water off," he said.
"They worked with our hydrology and hydraulics people
to figure out how many trees you could put in a certain length
of the bayou where it wouldn't affect how much water would
run off."
The bayou is "probably a lot greener" than it would
have been without the input of the environmentalists, deMasi
said. "Otherwise, it might be a big concrete channel."
|