|
A New Lease
What would have been the
fifth-tallest demolition in North America was scheduled after
a tornado struck The Tower office building in 2000. But then
the presence of asbestos saved Fort Worth's high-rise from
a flattened fate.
By Lesley Hensell
The transformation of The Tower from
trailblazing skyscraper to eyesore to penthouse living is
almost complete.
Originally opened in 1974, the 37-story Tower, designed by
John Portman of Atlanta for the Fort Worth National Bank and
built by Thos. S Byrne General Contractors of Fort Worth,
was one of the city's first skyscrapers, standing 454 ft.
tall. It served as an office building housing hundreds of
businesses over the years-until one dark and stormy night.
The memory still haunts many in the Fort Worth area. On March
28, 2000, a spate of powerful tornadoes hit the downtown area.
While The Tower survived and remained structurally sound,
a majority of its hundreds of windows were destroyed.
The Tower looked more like an old, abandoned warehouse than
a stately skyscraper and office building. The openings were
covered with plywood and metal panels, and the city began
its search for a solution.
To demolish, or not to demolish?
After detailed analysis, the answer was demolition. Refurbishing
the 487,000-sq.-ft. building appeared too expensive. A date
was set, and local retailers planned a festival called "Implosion
2001" to commemorate the fifth-tallest demolition job
in North America.
The implosion was halted, however, after it was determined
that asbestos flying from the demolition site would be too
hazardous to the public. What's more, after the terrorist
attacks on Sept. 11, the specter of a falling skyscraper,
paired with rising demolition insurance costs, made the plan
distasteful. Fort Worth was once again left staring at a boarded-up
skyscraper.
"That unfortunate series of events that made this building
a blight on the downtown Fort Worth landscape for so long
made it available for a second life, which I think is going
to be better than the first," said Brian George, principal
for Dallas-based Corgan Associates, which provided the design
team for the project.
TLC Realty Advisors provided the vision. The Fort Worth Company
teamed up with Greenfield Partners, a Cincinnati-based fund
adviser. The team envisioned converting the abandoned office
tower into a multiuse structure, in keeping with similar renovations
that have revitalized downtown Fort Worth over the last decade.
The team's plan included high-end apartments, condominiums,
30,000 sq. ft. of office space and 30,000 sq. ft. of retail
space. The partners purchased the building and negotiated
with the city, which agreed to pitch in nearly $17 million
toward renovations.
"When this particular building was designed in the 1970s,
the small floor plates were exactly what people wanted for
office buildings," said Tony Landrum, president of TLC
Realty Advisors. "As it turned out, the small floor plates
were ideal for residential use. It's also a center-core type
building, which you don't see much any more. But it was conducive
to our plans."
Then came the asbestos removal. Eighty-four columns on each
floor were coated in asbestos-laden plaster, and more than
$3 million was spent to cull the hazardous material from the
building. In total, abatement experts removed 23,000 lin.
ft. of nonfriable pipe material, 2,000 sq. ft. of surface
materials and 187,000 sq. ft. of miscellaneous regulated asbestos-containing
material.
From cold office to warm residence
Once abatement was complete, architects and builders faced
a significant challenge to transform the glass-and-steel,
octagonal building into a warm, welcoming residence.
"I wasn't very fond of the building in its original
iteration. It was a very stylized building, and it was brutal
with a very sheer, stark form," George said. "It
may have been an icon for Fort Worth, but it was certainly
a counterpoint to the Fort Worth vernacular of architecture."
The building's structure is visible in several places on
the exterior, thanks to a skeleton of concrete columns 5 ft.
on center. This continuous grid was exposed to give the outside
of the building texture, George said.
"On the interior units, the affect is incredibly open,
despite the amount of concrete that makes up the interior
walls," he said. "Because of the building's octagonal
shape, a high number of the units nestle into one of the angles
of the octagon. So almost all of these units have nearly 180-degree
views."
The team also added lighted panels to the top of the building.
The panels reflect sunlight during the day. At night, they
seem to float above the roofline and give the building the
appearance of being "crowned," George said.
To give the street-level entryway a warmer hospitable feel,
architects planned a five-story limestone base that extends
outward from the original building to the street.
"We wanted to make the building inviting to people who
were walking along the sidewalk," Landrum said. "The
only way to do that was to bring the building out to the street
on a scale that made sense. We essentially boxed out the original
atrium."
When the $65 million construction project began, the team
at Turner Construction of Dallas faced an unusual obstacle.
Because the building already stood 37 stories high, it was
nearly impossible to move materials where they were needed.
"Our biggest challenge was to move the 400 people working
on the project up and down the building in addition to the
amount of material we had to move," said John Reeves,
project executive for Turner Construction. "Because of
the way the columns were splayed at the bottom of the tower,
we couldn't put a material hoist outside."
Many materials could not fit into the building's elevators,
which needed to be used for moving workers.
"I've put tower cranes on virtually every building that
I've ever built, so I had to get a crane up there," Reeves
said. "In the past, the crane went up with the building."
Using the elevators, Reeves and his team transported a three-ton
derrick to the roof. That derrick was bolted down and used
to pull up an eight-ton derrick. In turn, that derrick was
used to raise a 35-ton derrick to the roof, which was mounted
and used to pull up the tower crane.
"Any renovation is tough because you are working with
an existing concrete structure and trying to make it do things
it was not originally intended for," Landrum said. "[The
original architect] over-elevated the building (too many elevators),
so we were able to take some of the elevators and turn them
into chases, which was critical for moving materials up and
down without sacrificing leasable floor space," he added.
When Turner began work, the building was completely gutted,
and its structure was sound. Glass and glazing began in January
2004. But due to a record year of rainfall, the building was
not dried in until June.
"There are 888 window openings on the building, half
of them curtain wall and half punched windows," Reeves
said.
Between the rain and a variance on electrical wiring that
had to be worked out with the city, the construction crew
found itself suddenly 30 days behind schedule.
"We pressed the subs to make up the time, and the next
thing we knew we were 30 days ahead," Reeves said. "Everyone
concentrated on getting the job done efficiently, and we really
made up some ground."
When the building owners began selling condominiums, they
discovered demand for a different mix of units. And so early
in the project, the planned apartments were scrapped. Instead,
the building will include 291 condominiums ranging in size
from 880 to 2,800 sq. ft., plus four penthouse condominiums
ranging from 2,800 to 5,500 sq. ft. The change affected 10
floors of units.
"Everyone had to stop, take a deep breath and re-look
at the efforts we had going in," Reeves said. "We
had the machine moving, with hundreds and hundreds of people
at work. All of a sudden we were trying to turn a battleship,
and those don't turn on a dime. It took a couple of weeks
to get reoriented."
Each unit was designed to admit natural light, a key to making
former office spaces look and feel more like homes.
"The building was relatively conducive to doing exactly
what we wanted to do," Reeves said. "I have to tip
my hat to the design team members. Their unit plan layout
allowed all of the plumbing risers to stack and the utilities
to stack."
The team placed boilers, chillers, cooling towers and heat
pumps for each of the 290 units. In addition to providing
standard layouts, the construction team had to offer customization
for each tenant.
"We started out anticipating between 300 and 400 upgrades,
but ended up with 3,000 items to choose from," Reeves
said.
Despite the customization and changes, Reeves expected to
complete the project ahead of schedule. Units are set for
delivery next month. Almost all of the building's 290 condos
have been sold, with the exception of a few units that were
built on spec to launch construction.
|
KEY PLAYERS
|
| Owner |
TLC
Realty Advisors, Fort Worth |
| General
Contractor |
Turner
Construction Co., Dallas |
| Architect
|
Corgan
Associates, Dallas |
| Electrical:
|
System
Electric Co., Plano |
| Mechanical
Systems |
Dyna
Ten Corp., Fort Worth |
| Glass
and Glazing |
Trainor
Glass Co., Fort Worth |
| Drywall |
Drywall
Interiors, Dallas |
| Masonry:
|
C&D
Commercial Masonry, Rowlett |
| Painting
and VWC |
L.H.
Land Painting, Mesquite |
| Materials |
Builders
First Source, Grand Prairie |
| Ceramic
and Quarry |
Lyn-Tile
Inc., Houston |
|