|
San Antonio's Big Lab Project
By Rob Patterson
Biotech, Sciences and Engineering
Building to Raises Research Bar at UTSA
The new Biotechnology Sciences and Engineering
Building III at the University of Texas at San Antonio was
designed to encourage and support multidisciplinary research
within a state-of-the-art facility.
"UTSA is positioning itself as a tier-one research university,
and we have the need to hire faculty and build research space,"
said Charles Lampey, director of facilities planning and development
for the university. "Right now we have faculty who don't
even have offices. So this building will take care of current
and future needs of the research presence on campus."
The facility is slated for completion in June.
The 227,000-sq.-ft. building will house
offices and teaching and research laboratories for the university's
colleges of science and engineering. Its research functions
and multidisciplinary mission mandated a high degree of internal
complexity within the structure.
The BS&E III building has a $60 million construction
cost. With its high-tech equipment inside, the total project
price tag will be $83 million.
The reinforced-concrete structure rises four floors above
ground with a sublevel and crawl space underneath. The concrete
pour was 16,537 cu. yds.
The first two levels feature a Texas Cordoba cream limestone
veneer. The third level exterior is plaster, and a glass curtain
wall wraps the top floor.
The building is capped with a sloped structural-steel frame
roof clad with red-clay tiles. "It pretty well follows
the master plan and the materials we've been using here on
campus for the past five years or so with new buildings,"
said Bob Evans, resident construction manager in San Antonio
for the University of Texas System.
Because the building is built into a hillside, workers faced
their first difficulties when excavation began in June 2003.
"The site falls from the north to the south some 20 ft.
through solid rock, and it took quite an effort to get all
that rock excavated," Evans said.
The location does help the structure blend into its surroundings.
"It's far and away the biggest building on campus,"
said Cynthia Walston, lead laboratory planner for FKP Architects
of Houston. "We didn't want it to totally overpower all
of its neighbors. So we built it into the hillside so one
of the levels disappears into the hill."
John Farrell, FKP's director of educational facilities, said
the building has three levels that mostly line up with the
levels of the other buildings on campus. "The glass curtain
wall around the top level makes it appear to float slightly,"
he added. "We think it will help it look not as massive
and ponderous a neighbor."
The on-campus site limited the laydown space for general
contractor Vaughn Construction Co. of San Antonio. "We
have our footprint and maybe 50 ft. to 60 ft. around us and
that's it," said Vaughn's project manager Bob Aniol.
"So everything has to be scheduled and brought in as
we need it."
Only 20 parking spaces were available for a crew of up to
350 workers on the project, prompting a creative solution.
"The different trades have given donations to the nearby
churches to use their parking lots," Aniol added.
Linking BS&E III to the university's master plant at
the other end of the campus was also daunting. "We had
to run chilled water pipe from the north side of campus underneath
three buildings while classes were going on and trench a 400-ft.
tunnel," Aniol said.
An intricate HVAC system provides a single-pass air-ventilation
system to the research labs with 100 percent supply and exhaust.
"It has twice as much ductwork as your average building,"
Aniol said. "There are two massive mechanical rooms in
the sublevel with 14 air handlers."
The sublevel also contains vibration-sensitive research equipment.
The solution was to sit some mechanical units on slab on grade
and others on structural steel mezzanines. "They are
internally isolated and sit on isolation pads," Aniol
said.
The basement also contains water-treatment equipment to serve
lab usage and treat waste. Because BS&E III sits atop
the environmentally sensitive Edwards Aquifer, Lampey said
special means of filtering and retention were installed.
Another mechanical penthouse underneath the roof helps ventilate
fumes from the hooded labs on the fourth floor. "That
way it's a very short run to get all the fume-hood exhaust
up and out," Evans said.
Walston said the university's regents were concerned about
exhaust stacks from the research building being visible. "The
red-clay tile roof really helps there," she added. "We
have an opening in the roof that the exhaust stacks come up
through at the necessary height."
The mechanical and plumbing feeds are also designed to be
adaptable. "The university wanted maximum flexibility
in the mechanical systems to be able to change a biology lab
into a chemistry lab," Walston said.
The design made the lab modules flexible, Lampey added. "We
even have faculty offices that could be future labs,"
he said. "Later on we could build an office building
at less dollars per sq. ft. and convert offices to labs."
A vivarium for holding live animals on the third floor features
advanced cage washing and watering systems. "It has its
own special piping with tanks in the sublevel," Aniol
said. Plywood and expanded metal behind the drywall are employed
to maintain the controlled environment and contain any animals
that may get loose.
A bridge from the third floor will connect with an existing
bridge that in turn connects with two existing science buildings,
providing a secure pathway for animal transport. "We're
going to bring all the steel material out and erect the bridge
on the ground," Aniol said. The 75-ft. assembly will
then be lifted by crane onto 32-ft. piers.
The interior was designed to serve the building's multidisciplinary
mission. Faculty offices are clustered on the first floor
along a central corridor to unite the various departments.
A ground-floor cafe with an outdoor patio also encourages
interaction.
"A real focus of this building was to create an environment
that would foster collaboration," Walston said. "One
of the things we did to encourage groups from different disciplines
to meet each other was put a four-story atrium with a monumental
stair in the center of the building to encourage chance meetings."
|
KEY PLAYERS
|
| Owner |
Lamar
Sixth Austin I Ltd., Austin |
| Developer/Director
of Design and Construction |
Schlosser
Development Corp., Austin |
| Anchor
Tenant |
Whole
Foods Market Inc., Austin |
| Tenant
Representative |
CDM/Project
Managers, Watsonville, Calif. |
| General
Contractor |
Hensel
Phelps Construction Co., Austin |
| Interior
General Contractor |
White
Construction Co., Austin |
| Architect |
HKS Inc.,
Dallas |
| Structural
Engineer |
Pickett
Kelm & Associates, Austin |
| Civil
Engineer |
Longaro
& Clarke Inc., Austin |
| Mechanical
& Plumbing Subcontractor |
Ideal
National Mechanical Corp., Round Rock |
| Mechanical
& Plumbing Engineer |
HMG &
Associates, Austin |
| Electrical
Subcontractor |
Hill
Electric Co., Austin |
| Electrical
Engineer |
Tolf
Wolf Farrow Inc., Newport Beach, Calif. |
| Landscape
Architect |
SWA Group,
Dallas |
| Excavation |
Ranger
Excavating, Austin |
|