|
Form to Market
By Rob Patterson
Flexibility Key in Whole Foods
New World Headquarters
Whole Foods Market is an Austin institution
that has grown from a cramped single store to an international
chain branded as the gold standard in natural and organic
foods.
The company was started by natural-food entrepreneurs John
Mackey, Craig Waller and Mark Skiles in 1980 in a one-story
box at Lamar Boulevard and Ninth Street on an occasionally
drenched flood plain. It migrated three blocks uphill in the
early 1990s and into a new corporate headquarters and sleek
flagship store at Lamar and Sixth Street.
Now the burgeoning Whole Foods Market operation is jumping
one block farther south into a 280,000-sq.-ft. showplace supermarket
and six-story office building that signals its status as the
leader in its field.
Flexibility has been a byword of the quest to provide Whole
Foods Market with what it calls its "landmark" supermarket
- the largest of its 162 stores in North America and Great
Britain - as well as a state-of-the-art world headquarters.
A different project was originally planned for the site by
Austin-based Schlosser Development Corp. for the property
owner, Lamar Sixth Austin I Ltd.
"We had a fully permitted different
scheme for both that block and the block next to it,"
said Rick Duggan, director of design and construction for
Schlosser. "It was to be a Target store under three levels
of retail adjacent to a 1,700-car garage, all of which was
to be under a 20-screen movie theater.
"For a variety of reasons, which included tenancies
going bankrupt or choosing to take smaller spaces, that project
stalled."
During the stall, which occurred in 2002, Schlosser got together
with Whole Foods. "They approached us and everything
started to make pretty good sense. I think we have a spectacular
project for them," said Duggan, who added that the overall
project will cost in the neighborhood of $50 million.
Schlosser will acquire the property Whole Foods is vacating,
and the company will develop the multiblock area around the
new Whole Foods headquarters as a "Market District."
Integrating the needs and vision of Whole Foods into a new
project wasn't easy. "It's almost a Rubik's cube,"
said Owen McCrory, design architect for HKS Inc. of Dallas.
What they are trying to do is stack a 200,000-sq.-ft. corporate
headquarters on top of an 80,000-sq.-ft. store, which then
sits on top of 800 parking spaces-all on one city block in
a relatively urban area."
The team has numerous principal players. The Austin office
of Hensel Phelps, which is headquartered in Greeley, Colo.,
is the shell contractor; two divisions of White Construction
of Austin are finishing out the store and the office tower.
Whole Foods holds a long-term lease on all but one of the
office floors and had substantial user input. The company
engaged CDM/Project Managers of Watsonville, Calif., to oversee
the project.
There were revisions as the planning and construction progressed.
"There have been quite a few significant changes on this
project," said Kevin Karr, project manager for Hensel
Phelps. "The design was an evolving process."
"Working with the creativity and input from the Whole
Foods people as a tenant has generated a lot of tweaks and
interactions: 'Add a skylight, move a parapet, work through
this equipment location, add a mezzanine for our refrigeration
equipment,'" Duggan said. "In many aspects it has
become a build-to-suit."
For Hensel Phelps, the initial excavation phase of its $38
million building project presented the toughest hurdles after
the May 2003 groundbreaking. To accommodate the three-level
cast-in-place concrete underground parking garage, crews had
to "dig 40 ft. down into solid limestone" Karr said.
"We had about 150,000 cu. yds. of material come out of
the hole, and three-quarters of it was limestone."
Austin-based Ranger Excavation brought out the heavy equipment.
"Ranger had several Caterpillar D11's out there, rock
saws, milling machines and three or four track hoes with hoe
rams, all ripping rock and taking it out one piece at a time,"
Karr said. Compounding the challenges was access to the site.
Removals and deliveries had to be woven through commuter traffic.
A utility and road reconstruction project was under way simultaneously
along Lamar Boulevard. "We did all our concrete placements
at night so we wouldn't be trying to bring hundreds of concrete
trucks to the job site," Karr said.
About 29,000 cu. yds. of concrete was poured for the garage
and foundation.
Above the ground, the structural-steel frame was fortunately
purchased prior to the 2003 price hikes. "But there were
some problems getting light-gauge metal-stud framing,"
Karr said. The skin it frames above the first level is a mix
of terracotta-style tan-and-slate exterior-installation-finish
system and nonreflective glass. "Our plan was to build
the skin of the office up, but we're building it top down,"
he added. "We resequenced so we could get the roof on
and top floors dried in."
The top two floors feature all-glass window walls, which
helped the contractor overcome the framing hitch.
"Hensel Phelps had the foresight to build in a Fraco
exterior scaffold lift system," Duggan said. "So
the delay in the studs didn't hurt us badly because the contractor
had already built in flexibility with staging and the scaffolding
system. Top down became the order of the day."
HKS developed specific approaches for the office building
to make it work in harmony with the store below and the site.
"What we've created is a very large footprint building,"
architect McCrory said. "It's more than 2000,000 sq.
ft. We wanted to make sure that large footprint didn't dominate
over the store."
Whole Foods employee input called for outside light and views.
The solution, introduced after planning and design, is an
L-shaped tower with the elevator bank, stairwell and an HVAC,
utility and plumbing shaft at the juncture of the L. The absence
of interior walls means that "no work area is more than
45 ft. from a window," Duggan said.
Top-to-bottom curtain walls grace the office structure's
corners. The largest of them adjoins the office tower's two-story
entrance on Sixth Street. The office tower also features a
modular raised-floor system with the HVAC delivery and utilities
running underneath that gives each worker an individual air
vent control at his or her desk.
It is estimated that the design will result in a 30 percent
savings on air-conditioning costs. And the flexibility of
the modular system with its plug-and-play electrical connections
allows Whole Foods to easily reconfigure office space in the
future.
On the ground level, stucco and Leuters limestone clad the
building. The storefront facing Lamar features a "market
hall" and a gently curved entryway with a window wall
that mixes clear panels with yellow, green and blue tinted
panes.
Another aspect added as the building developed was the variety
of store access options to and from the parking garage. Elevators,
escalators and stairs carry shoppers into the store. A moving
sidewalk at an approximately 30-degree incline with a magnetic
system to secure shopping carts allows customers to wheel
their purchases to their parking spaces. Or shoppers can choose
to have their groceries transported down by conveyor and loaded
into their vehicles.
A plaza leading to the storefront also offers 115 spaces
of surface parking and features live tree plantings, tree-shaped
trellises, shaded outdoor dining areas, a simulated Hill Country
stream and a pick-your-own herb garden.
Another public plaza sits atop the store, reached by a stairway
graced with more plantings and shade structures. And in typical
Austin fashion, there's also a performance stage.
|
KEY PLAYERS
|
| Owner |
Lamar
Sixth Austin I Ltd., Austin |
| Developer/Director
of Design and Construction |
Schlosser
Development Corp., Austin |
| Anchor
Tenant |
Whole
Foods Market Inc., Austin |
| Tenant
Representative |
CDM/Project
Managers, Watsonville, Calif. |
| General
Contractor |
Hensel
Phelps Construction Co., Austin |
| Interior
General Contractor |
White
Construction Co., Austin |
| Architect |
HKS Inc.,
Dallas |
| Structural
Engineer |
Pickett
Kelm & Associates, Austin |
| Civil
Engineer |
Longaro
& Clarke Inc., Austin |
| Mechanical
& Plumbing Subcontractor |
Ideal
National Mechanical Corp., Round Rock |
| Mechanical
& Plumbing Engineer |
HMG &
Associates, Austin |
| Electrical
Subcontractor |
Hill
Electric Co., Austin |
| Electrical
Engineer |
Tolf
Wolf Farrow Inc., Newport Beach, Calif. |
| Landscape
Architect |
SWA Group,
Dallas |
| Excavation |
Ranger
Excavating, Austin |
|