|
Quiet Determination at UT
Where There's a
Wire Saw, There's a Way
By Jeff Hawk
There's nothing like the reverberating
sound of a jackhammer to focus the mind on academic pursuits.
Fortunately for University of Texas at Austin students, UT
officials disagree. The partial demolition of UT's Batts Infill
Building could have been a dusty, disruptive affair. But the
rare use of a diamond-beaded wire saw minimized the mess.
 |
|
All that's left of the old Batts Infill
Building are the walls
|
The project called for gutting the narrow
60 by 100-ft. structure, leaving only its historic Texas shell
limestone exterior walls. The building "fills in"
the space between the newly renovated and presently occupied
Mezes Building and the currently under-renovation Batts Classroom
Building. The work included removing two levels of structural
elements supporting the existing auditorium and classrooms.
Glenn Horstmann, project manager for UT's selected construction
manager SpawGlass Contractors Inc., said demolishing the structure's
interior is "like working in a shoebox."
The Austin office of SpawGlass finished renovating the Mezes
and adjacent Benedict buildings last year as part of a two-phase
$33 million contract to modernize, re-configure and add on
to existing structures within UT's South Mall buildings. The
rapidly growing university needed more classrooms, more office
space and to bring their outdated buildings up to code, Horstmann
said. Built in 1952, the buildings fall under historic preservation
requirements stipulating that their exterior walls must remain
untouched. In September SpawGlass began the second phase,
which includes renovations to the 24,000-sq.-ft. Batts Infill
and the 80,000-sq.-ft. Batts Classroom buildings.
The smaller building posed the bigger challenge. SpawGlass
had to demolish Batts Infill's 3-ft.-thick and nearly 2-ft.-wide
structural concrete beams while causing minimum disturbance
to Mezes occupants and minimal damage to the structure's historic
walls. Jackhammers and air hammers would typically do such
demolition work. But the vibrations, noise and dust caused
by such equipment and concerns about weakening the walls forced
SpawGlass and its demolition contractor, Southwest Destructors
of Austin, to think outside of the box.
|
The wire saw provided the solution. The
saw uses a diamond-embedded stainless steel cable to loop
around the heavy beams. A 24-in.-diameter composite metal
wheel drags the cable across the concrete member while a feed-pulley
system draws it in. The speed is generally slow but adjustable.
Rubber spacers protect the cable; water from a hydraulic pump
cools it while it cuts. The device produces little dust and
minimal vibration, said David Day, an estimator for Austin-based
Austex Drilling and Sawing Inc., which provided and operated
the saw for Southwest Destructors.
Perhaps most important, the wire saw greatly reduced the
potential of "microscopically cracking" and structurally
damaging the existing walls, Day said. Vibrations from air
and hydraulic hammers can weaken structures by "separating
the steel from the concrete," he added. Wire sawing is
faster, safer and more cost-effective than traditional methods,
but "it's not often used," Day said.
Prior to cutting, crews assembled a forest of shoring up
to the concrete beams and used existing steel bar joists from
the roof to build mid-wall box trusses that supported the
existing structure.
Workers "hopscotched" the demolition, said SpawGlass
project superintendent Jim Williams, referring to sequencing
the repeated process of tearing out the 7.5-in. concrete slab
floors, building the box truss and then cutting and removing
the beam. A tower crane carefully lifted the huge 17-ft. long,
7.5-ton beam sections out of the mesh of trusses and scaffolds.
"What they came up with was clever," said Bob Rawski,
senior project manager for UT's facilities, planning and construction
office.
The new Batts Infill Building will house four levels of classrooms
and offices. A gabled roof surfaced with UT's signature orange
clay Ludwici tile will replace the structure's original flat
metal roof and provide attic space for mechanical elements.
Crews will excavate down 8 ft. to 10 ft. to make room for
sub-soil drainage installation.
SpawGlass is simultaneously renovating the connecting Batts
Classroom Building. Both structures will receive new fire
suppression, fireproofing and fire alarm systems to replace
the antiquated fire-hose cabinets. Mechanical and electrical
upgrades are also planned.
Some interior features will stay including black marble accents,
travertine-tile stairways and glazed wall tiles. The removal
of some historic features, such as the buildings' original
plywood stamped with the words, "Made in Occupied Japan,"
signify the end of an era just as the installation of a modern
top-of-the-line security system signifies the dawn of a new
one.
|