|
Net Worth
Frisco Reaching Goal With New Soccer &
Entertainment Center
by Rob Patterson
Frisco city planners and private
partners desired a sports complex that would also have a positive
economic impact on the surrounding area. The vision kicks
off next month with the opening of the Frisco Soccer &
Entertainment Center.
With an August opening planned for its new $65 million Frisco
Soccer & Entertainment Center, the Dallas suburb will
kick another scoring point toward the goal of becoming a North
Texas sports center.
Sited on 144 acres adjacent to the North Dallas Tollway and
north of the city's Entertainment and Sports Complex, the
20,000-seat multipurpose stadium with 17 adjoining soccer
fields adds the Major League Soccer team, FC Dallas (formerly
the Dallas Burn), to the team of other Frisco sports franchises
including the Texas Ranchers' AA affiliate Minor League Baseball
team the RoughRiders and the North American Hockey League
team Texas Tornado.
Construction began in April 2004 under a guaranteed-maximum
price contract. General contractor Lee Lewis Construction
Co. of Lubbock had to complete the facility in time for the
first game on August 6.
"Between June and November of last year we lost 63 days
to weather, and it put us behind," said Gary Tanner,
the firm's project manager.
After the excavation of 200,000 cu. yds. of material to create
the 35-ft. deep bowl where the field sits, rainfall deposited
8 ft. of water inside it, covering the cab of a crane pouring
some of the 30,000 cu. yds. of concrete for the sloped bleachers
above either side of the soccer pitch.
"We had three 6-in. pumps that displaced 120,000 gallons
an hour going 24 hours a day trying to get that thing emptied
so we could work," Tanner said. Nearly 5 million gallons
were pumped out.
Once the stadium was dry, high-grade
natural turf was laid atop 16 in. of gravel and sand fill.
A 250,000-gallon concrete retention tank with lift pumps will
guard against future flooding.
The below-grade design was important because of the nature
of the game. "One of the reasons for going down into
the ground was that soccer has no timeouts," said Gary
Stockwell, project architect with Dallas-based HKS Inc. "The
only opportunity for fans to get a break from the action is
halftime."
So a concourse was created around the stadium with views
down to the field and concession stands and restrooms that
face the field, Stockwell said. The idea was for fans to be
able to leave their seats while still being able to see the
field and be part of the action.
"If you go up with a stadium, you have to go back underneath
the seats to get to the concessions and you can't see what's
going on," Stockwell added. "And dollarwise it's
sometimes more economical to go down rather than up, depending
on what you run into with your ground conditions."
Nearby development in the booming suburb also influenced
the design. "The new town center across the street is
a maximum of four-story buildings," he said. "So
we fit in that same vocabulary."
On the stadium's west side is a three-story, 38,000-sq.-ft.
clubhouse with 26 luxury suites on the second story and press
boxes and game operations on level three. The structure is
steel frame on concrete pad faced with window wall, plaster
and concrete masonry unit topped by a steel roof. The private
boxes will have a shaded balcony in front of them.
Two one-story concession buildings totaling 38,000 sq. ft.
curve around the southwestern and southeastern sides of the
bowl. They are built of CMU atop concrete slab with a skin
of plaster and metal panels between split-face CMU columns
and a steel roof. All of the structures will have standing-seam
steel roofs.
"We used a lot of colored CMU and cement plaster because
it fits with a vernacular that Frisco has," Stockwell
said. "It has a bit of a Texas Hill Country theme."
The simple design and basic materials of the stadium buildings
suit its usage pattern. "One thing is that you want is
materials that are durable," Stockwell added. "And
they have to be easy to basically lock the doors and walk
away from."
Tanner said teamwork was important to come up with a building
that was not only nice looking but practical. Luckily, HKS
had previously worked with Tanner (then with Manhattan Construction
Co.) on the Texas Rangers' Ameriquest Field in Arlington.
A 22,000-sq.-ft. concrete stage at the north end of the field
was added in the planning stages to host concerts and other
events. A structural-steel proscenium topped by a steel canopy
will be used to fly lighting and sound gear.
On the east side of the stage is a 15,000-sq.-ft. underground
reinforced-concrete truck bay that can accommodate five semis
and/or tour buses. Above it will be a 21,000-sq.-ft. two-story
structural steel frame office and commissary building.
An 8,000-sq.-ft. underground concrete tunnel on the northwestern
end of the stadium gives players access to the field. Above
it will be a 42,000-sq.-ft. steel-frame locker room and an
office building above that (the final size and the number
of levels of the structure are not yet finalized). Both buildings
will have a skin of glass, split-face CMU and plaster and
metal panels with a steel roof.
The ground on the site needed extensive work before the buildings
could be erected.
"It's heavy clay with terrible swell potential,"
Tanner said. "We had to do moisture conditioning down
to 10 ft. to maintain its firmness."
Lee Lewis is also installing irrigation systems, lighting,
fencing and roadways as well as laying fill and turf for the
17 other soccer fields. A total of 150,000 sq. yds. of natural
turf and 32,000 sq. yds. of synthetic turf on three other
fields is being installed. Two retention ponds were built
to control runoff and supplement the two wells dug for supplying
water to the fields.
The job also includes paving 40 acres of parking for games
and events.
Even on the large site, laydown space eventually became limited.
"You'd think on a 100-plus acre site that wouldn't be
a problem, but after the fields were laid down, it actually
was," Tanner said.
The $65 million cost of the complex was financed by a consortium
of local partners. Contributors include the city of Frisco,
Colin County, Frisco Independent School District, the Frisco
Economic Development Corp., the Frisco Community Development
Corp. and Dallas-based Hunt Sports Group, which operates the
FC Dallas soccer franchise.
"It's a great financial partnership having the school
district involved," said Scott Young, Frisco assistant
city manager. "Facility usage will be maximized by also
hosting Frisco ISD soccer and football games, and it saves
the district the cost of building its own sports stadium."
Hunt Sports Group will lease and manage the complex under
an initial 20-year contract. A variety of soccer activities
including training, local club games and national tournaments
are planned for the complex.
"The Hunt Sports Group worked with the contractor and
architect to produce a fantastic facility," said Billy
Ray Johnson, vice president of construction management for
Hunt Sports. "It definitely was a group effort."
The city is also supplementing the project with infrastructure
improvements such as new roads around the complex. "It's
going to be great for the area," Young said. "And
it's going to generate a lot more business."
|
Key Players
|
| Owner |
City of Frisco |
| General Contractor |
Lee Lewis Construction Inc., Lubbock |
| Architectural and Engineering:
|
HKS Inc., Dallas |
| Tenant/Operator:
|
Hunt Sports Group, Dallas |
|