|
Housing the Mean Green Becomes a
Victory for All
By Chuck Nixon
 |
| Chuck Nixon, AIA, is principal,
vice president, facilities division, Carter & Burgess,
Fort Worth |
When swelling enrollment stretched
the demand for on-campus housing at the University of North
Texas in Denton, its administration set an ambitious goal
of opening the new 600-bed Victory Hall within 18 months.
After evaluating more than 20 candidates, the university
selected Carter & Burgess to serve as the prime architect/engineer
along with design partner Architecture Demarest of Dallas,
a firm with experience in designing facilities for more than
50,000 student beds nationwide.
From the onset, the new design team committed to an aggressive
five-month schedule allowing for a guaranteed-maximum-price
construction-manager-at-risk process and 13-month construction
duration.
Access to senior university administrators allowed the architects
to start certain parts of the project before other parts were
fully designed. This was instrumental in meeting the demanding
schedule. While Architecture Demarest was tweaking with the
room's exact dimensions, for example, mechanical and electrical
engineers from Carter & Burgess were given the approved
final building layout so they could begin their design.
 |
| The University of North
Texas in Denton project proves that sleek, modern facilities
don't have to break the budget of public institutions. |
The team didn't have the luxury of time for the linear process
so; the integration of A/E disciplines helped the team meet
the tight deadline.
The Carter & Burgess/Architecture Demarest team began
the design process by looking at all the systems to determine
how to get the project to budget, including simplifying the
overall design where possible without sacrificing function
and programmatic goals.
The new structural system and resulting changes to the foundation
resulted in a savings of almost $2 million over a conventional
structure and four to six weeks off the schedule. The system
also features a long lifespan, which is favored by public
education institutions. A conventional concrete structure
was replaced by a panelized steel-studded wall and floor system,
which used framing units much like residential wood walls.
The system panels consisted of light-gauge metal studs placed
two ft. apart from each other, and layered with a corrugated
metal deck and poured concrete.
Time and cost efficiencies were further realized because
the steel wall panels were manufactured off site and then
erected.
The new structural system and resulting changes to the foundation
shaved almost $2 million and four to six weeks off the schedule.
The system also features a long lifespan, which is favored
by public education institutions.
Another way the Carter & Burgess/Architecture Demarest
team reduced costs early in the design process was to use
one signature tower in lieu of two as originally conceived
and using a fiber cement siding in lieu of brick on interior
courtyard walls.
Design revisions carved $4 million from the total construction
cost, and the team's close collaboration with the university
administration allowed the project to be constructed within
10 months, meeting the August 2004 opening date.
Victory Hall provides the modernity that appeals to students
while providing an affordable product desired by the public
higher-education community. Its two U-shaped limestone and
brick buildings are three and four stories tall, have access
to two courtyards and are topped with a green composition
roof to symbolize the university's "Mean Green"
athletic team motto. A 12,000-sq.-ft. community space with
a cyber café, audio/visual room and an indoor recreation/
lobby/reception area connects the buildings. The students
affectionately refer to this area as "the terminal."
As a model of the university's pride, it also serves as a
recruitment tool as the university seeks to expand enrollment
and attract student athletes.
|