Steel
Shortage Creating New Trials for Texas Contractors, Suppliers
While existing contracts face
supplier price increases and delivery slippages, new projects
without price-escalation protection will need to consider how
to cover the recognized risk associated with the volatile pricing
of steel products.
By Joseph Dirik, Esq.
The current steel shortage has prompted some owners to add
a steel-price escalation clause in their new contracts. Bidders
on new projects without price-escalation protection must decide
how to cover the recognized risk associated with volatile
pricing of steel products. In the meantime, how will the industry
deal with price and delivery problems on existing contracts?
Suppliers unable to purchase material as planned will probably
demand their performance be excused or compensation increased.
A suitable force majeure clause in the material contract might
end the discussion. But material purchase orders often used
by contractors usually do not include language dealing with
force majeure. Therefore, courts and arbitrators will likely
be called upon to resolve such disputes. Resolution will require
balancing a wish to grant relief to a contracting party with
the need for commercial certainty in contracts.
A party seeking relief from a breach will likely claim the
defense of impossibility or impracticability. True impossibility
is rare. Commercial impracticability, however, involves performance
that cannot be accomplished without excessive and unreasonable
cost. Under Texas' Uniform Commercial Code, resulting unforeseen
supervening circumstances not contemplated by the parties
may excuse a supplier's performance. Suppliers should be award
of questions that must be answered prior to being excused
from a contract. For example: When the contract was made,
could the parties have foreseen the occurrence and severity
of the steel shortage? Did the supplier assume the risk of
steel shortages either expressly or tacitly? Given the commercial
circumstances surrounding the contract, could the parties
have reasonably foreseen the eventual effect of the steel
shortage?
The last major steel-industry crisis occurred in the 1970s.
One Texas case that came about as a result of the shortage
was in 1974, when J. D. Abrams Inc. encountered delivery problems
with its steel supplier on a TxDOT bridge project. Despite
the steel shortage, the El Paso Court of Appeals in Robberson
Steel Inc. v. J.D. Abrams Inc. found that the supplier was
responsible for Abrams' costs resulting from a six-month delay
in delivering the steel. The Court affirmed the trial court's
finding that delays in receiving steel from the mills was
a contingency which the parties could reasonably have foreseen
and one of the risks the parties tacitly assigned to the supplier.
Robberson's bid included a disclaimer stating "delivery
is subject to our ability to procure steel from our steel
mill suppliers." But after checking with supply sources,
Robberson chose not to incorporate the disclaimer into the
purchase order. The evidence further showed that Robberson's
purchasing manager confirmed availability with the mills before
the state bid letting and again after he learned that Robberson
was the successful bidder. The Court determined that Robberson
was concerned with delivery before it entered into the contract
with Abrams. According to the Court, the evidence showed that
delivery from the mill was "very definitely a circumstance
within the contemplation of the parties at the time the contract
was made," and Robberson's delayed performance was not
excused.
While courts cannot simply rewrite the parties' contract,
performance can be excused in circumstances in which both
parties held a basic (though unstated) assumption about the
contract that proves untrue. Consider this example: A manufacturer
has a contract to sell its product, but the factory that makes
the product is destroyed. Under these facts, the manufacturer
is still bound to the contract so long as the product is available
elsewhere. But the manufacturer's performance might be excused
if the parties understood that material from the destroyed
factory must be used to fill the order. This provides an example
of a basic assumption under the contract, shared by both,
that cannot come true.
A party claiming commercial impracticability must also use
reasonable efforts to overcome the obstacle to fulfill performance.
In the previous example, the manufacturer must attempt to
purchase replacement products to satisfy its contractual obligation.
In searching for ways to overcome the obstacle, increased
cost alone generally does not excuse performance. But a marked
increase in cost resulting from a severe shortage of raw materials
might. How great that increase must be is yet to be answered
by the courts, and will depend on the circumstances surrounding
the shortage and the individual facts of each dispute.
Parties involved in disputes regarding the steel shortage
should exercise great care in their actions. A successful
claim of commercial impracticability might excuse a contract
breach, but is very difficult to evaluate in advance. Under
the UCC, a party can breach it's a contract by taking action
that reasonably indicates rejection of continuing obligations.
Before taking any action that might be viewed as an anticipatory
breach of your contract, be sure to consult your attorney.
|