|
Analyzing Delays
By Joseph P. Dirik
Joe Dirik is a graduate civil engineer and attorney. He is
a member of the construction law practice group at the Dallas
office of Jenkens & Gilchrist, PC.
Excusable delays are usually identified in a contract and
include unreasonably severe weather, owner-caused delays and
other events outside the contractor's control. Contractors
are generally entitled to time extensions for excusable delays.
Delays are an inevitable part of most construction projects
and usually considered excusable and non-excusable.
The burden to prove the number of days requested in an extension
usually falls on the contractor. Many contracts require the
use of Critical Path Method schedules and spell out how the
contractor must calculate and present time-extension requests.
A CPM schedule's effectiveness is directly related to the
initial detail and effort expended to set up and monitor the
schedule. To be effective, the contractor must plan the project
from the beginning to ensure the schedule's logic reflects
the manner the contractor plans to build the job.
A CPM schedule prepared without involving superintendents
and other staff who will be assigned to build the project
may be ineffective.
A friend, who previously estimated and managed slip-form
projects, always put a lot of effort into planning. He would
often prepare a detailed CPM schedule for the estimate and
proposal, carefully identifying and planning each pour, associated
rebar and formwork activities. He put so much time and effort
into the project, even at the bidding stage, that there was
little doubt about how he planned to build the project. Because
his logic was usually sound, he could easily resolve delay
issues with his customer.
Many times extension requests involve the issue of concurrent
delays, or delays attributable to the owner and contractor
during the same period. In some states, neither party can
recover damages. Texas allows a party to recover concurrent
delays only if the delays can be apportioned between the parties.
Concurrent delays do not need to actually take place at the
same time. The party claiming the delay damages must prove
a reasonable basis for apportioning the effects of concurrent
delays.
Only a delay affecting the critical path qualifies as a concurrent
delay. Delays to activities with float cannot, by definition,
delay the project.
Does your analysis involve one activity with multiple delays?
If so, the CPM schedule should identify the total delay but
will be of little use in apportioning potentially concurrent
delays. For example, an owner could order a change impacting
performance of a scheduled activity, but the contractor could
have caused concurrent delays in performing the affected work.
In these cases, the facts surrounding the delay will determine
the existence and apportionment of any concurrent delays.
The schedule analysis will report the total delay.
Does your analysis reveal multiple activities and two or
more delays? The key step is to determine whether either delay
is affecting the critical path, or both. I worked for a firm
involved in the first Contract Appeals Board decision on concurrent
delays. Fischbach and Moore International Corp. contracted
with the Voice of America to erect 104 steel radio towers
in the Philippines and presented a claim for project delay.
The VOA placed a hold on work to a particular portion of the
towers. In its 1976 decision, the Corps of Engineers Board
of Contract Appeals recognized 161 days of total delay and
held that 114 days of that period were the government's responsibility.
The board examined the suspension's impact on Fischbach's
overall progress and concluded that the design change by the
government "was solely responsible for the frustration
(of the contractors') plan of attack on tower erection."
The board determined that the financial difficulties of one
of Fischbach's critical subcontractors prevented that subcontractor
from performing any effective work, and that this represented
a concurrent delay for which no compensation was allowable.
The concurrent delay period ended when the contractor cured
the subcontractor's problems by taking over the work itself.
Another example: An owner issues design changes to a building's
foundation. The order is followed by a delay in the structural
steel delivery. The contractor would argue that in the face
of a known delay by the owner to the foundation work, the
contractor was not concerned with the supplier's delivery
slippage. Dependent or independent delays? Cases in other
jurisdictions hold that in these situations, the burden shifts
to the owner to demonstrate that the contractor's original
schedule, which was not followed after an owner-caused delay,
could not have been met even if the owner delay had not occurred.
|