|
Substantial Completion and Substantial
Performance
By Joseph Dirik, Esq.
The author writes that if a contract
does not define or permit substantial completion, a contractor
may still recover for the majority of its payments if it has
substantially performed.
Joe Dirik is a graduate civil engineer and attorney.
He is a member of the construction law practice group at
the Dallas office of Jenkens & Gilchrist, PC.
Every contractor seeks to reach substantial completion on
a project at the earliest opportunity. In many contracts,
substantial completion entitles a contractor to receive most
of its payment, and escape responsibility for liquidated damages.
Substantial completion is generally a contract milestone,
and often determined by the terms of the contract.
Substantial performance is a similar concept. Texas common
law generally requires strict compliance with the terms of
a contract. This means that a party seeking payment for its
performance must have fully performed before it would be entitled
to full payment. The rule has been modified for building and
construction contracts by the doctrine of substantial performance.
It is an equitable doctrine adopted to allow a contractor
who has substantially completed a construction contract to
sue on the contract for the owner's failure to pay. The doctrine
is important to contractors because the owner cannot use the
contractor's failure to fully complete the work as an excuse
for non-payment. Substantial performance also requires the
contractor to have, in good faith, intended to comply with
the contract, and have substantially done so.
When a contract does not define substantial completion, substantial
completion is often considered the stage when the project
is "ready for its intended use." What does this
mean if not defined in the contract? One could determine a
project's intended use if it involves a manufacturing facility
that requires performance tests to demonstrate that the facility
is ready to produce. An office building may be ready for its
intended use when issued a certificate of occupancy. The best
practice for determining substantial completion is to include
an express definition in the contract.
Using the example of a manufacturing facility, it would be
easy to define substantial completion as that point in time
when the facility produces the product or completes the process
for which it was designed. In other contexts, it may be necessary
to rely on "satisfaction" clauses, which permit
an owner or the owner's agent to refuse acceptance of the
work until the performance or aesthetics of the project meet
the owner or its agent's satisfaction. Satisfaction clauses
are usually based on an objective or subjective standard.
Under an objective standard, a reasonable person must have
been satisfied. A subjective standard is based on the judgment
of the individual who must be satisfied. In Texas, satisfaction
clauses generally require the owner act in good faith when
claiming dissatisfaction.
Standard form contracts address substantial completion. For
example, under Section 8.9.1 of AIA A201-1997, the contractor
determines when the work is "sufficiently complete in
accordance with the contract documents so that the owner can
occupy or utilize the work for its intended use." If
the contract does not define intended use, the contractor
might face the problems noted above. A well-prepared contract
should define intended use or provide substance to permit
a contractor to determine when a project is substantially
complete.
If its contract does not define or permit substantial completion,
a contractor may still recover for the majority of its payments
if it has substantially performed. The contract definition
of substantial completion is always the first step. A Texas
Court of Appeals case, Coastal Chemicals, Inc. v. Brown, dealt
with a poorly drafted substantial completion provision. The
contract provided that the contractor would be entitled to
an early completion bonus if the project was substantially
completed by a specific date. The contract did not define
substantial completion. The contractor argued that it had
successfully installed the improvements by the substantial
completion deadline. After discovering latent defects in equipment
that prevented the plant from operating, the owner refused
to pay the bonus. The court agreed with the contractor, and
awarded the bonus. It found the owner had accepted the contractor's
work as substantially complete. The court determined the owner
would have to rely on the contract's warranty provisions to
address latent defects.
In Texas, substantial completion, therefore, generally deals
with how the contract defines this important milestone. Substantial
performance, on the other hand, is an exception to the common
law rule requiring strict performance of contracts in construction
and building projects.
|